Versions Compared

Key

  • This line was added.
  • This line was removed.
  • Formatting was changed.

Availability

(assume Team Availability Calendar is up to date, otherwise, everyone was available for 7.5 days (1 Bank holiday) of the 2-week Sprint)

Full team availability 7.5-day Sprint * 8 dev team members60 days
Andy, Yafang, JohnO, Simon, Ola, Jay, Pepe, John


Total team availability this Sprint79%



POs present a review of Sprint goals and other committed work



Sprint Goal: 
Major improvements to ESR
  • Note there was no subsidiary work this Sprint - it was our first 'Themed' Sprint, enabling the whole team to focus their efforts on one specific part of the codebase.



POs supported by Dev team provide narrative on why, and what, emergency work was brought into the Sprint and which committed-to tickets were moved out as a result


Live Issues:

Jira Legacy
serverSystem JIRA
columnskeytype,summary,type,created,story points (effort),assignee,created
maximumIssues20
jqlQueryproject = TISNEW AND issuetype = LiveDefect AND Sprint = 189 order by created DESC
serverId4c843cd5-e5a9-329d-ae88-66091fcfe3c7


Dev team demo 'done' work contributing to those goals (no more reference to specific list of Jira tickets, and no more reference to work not 'done')



ItemDemo - from Prod URL were feasibleDemo link

1.

Users cannot search or filter on all trainees at their local office - Oladimeji Onalaja (Unlicensed)


Jira Legacy
serverSystem JIRA
serverId4c843cd5-e5a9-329d-ae88-66091fcfe3c7
keyTISNEW-2993

2019-05-17 Users cannot search or filter on all trainees at their local office

2.

ESR - performance (SQL refactor) - Joseph (Pepe) Kelly
3.

ESR - No APP Files generated by the TIS-ESR ETL Oladimeji Onalaja (Unlicensed)


4.

ESR - Investigation on handling multiple applicants per deanery number in the DNF/C Files


5.

ESR - Daily Notifications Load for Large Numbers


6.

ESR - ETL Notification date coverage


7.TIS-ADMINS-UI - Security vulnerability Oladimeji Onalaja (Unlicensed)
8.ESR Applicant Export Failure 21st May 5pm Joseph (Pepe) Kelly



Stakeholders / Users invited to query / interrogate / applaud (after Sprint Review POs convert consensus inputs into backlog tickets, giving the option to consider them in the coming Sprint Planning)



POs present the roadmap