Availability

(assume Team Availability Calendar is up to date, otherwise, everyone was available for 8.5 days of the 2-week Sprint)

Full team availability 8.5-day Sprint * 8 dev team members68 days
Andy, Yafang, JohnO, Simon, Ola, Jay, Pepe, John


Total team availability this Sprint92%



POs present a review of Sprint goals and other committed work



Sprint Goal: 
Complete sync service and focus on a Revalidation workshop - to determine the plan of attack.
  • Security fixes
  • Trust ID fix
  • Sanitizer (special characters)
  • Rotations fix
  • Monitoring
  • Service Status



POs supported by Dev team provide narrative on why, and what, emergency work was brought into the Sprint and which committed-to tickets were moved out as a result


Live Issues:

Jira Legacy
serverSystem JIRA
columnstype,summary,story points (effort),assignee,created,status
maximumIssues20
jqlQueryproject = TISNEW AND issuetype = LiveDefect AND Sprint = 192 order by created DESC
serverId4c843cd5-e5a9-329d-ae88-66091fcfe3c7


Dev team demo 'done' work contributing to those goals (no more reference to specific list of Jira tickets, and no more reference to work not 'done')



ItemDemo - from Prod URL where feasibleDemo link

1.

Remove the Synchronisation jobs within TCS and build a separate Synchronisation service (??)


2.

Reval (& Concerns and Notifications) rebuild architecture workshop (Alistair)


3.

TIS-ADMINS-UI: Security vulnerabilities (Ola and JohnO)

Bootstrap and Webpack-Bundle-Analyzer: Needed to be addressed because it opened our app to Cross-Site Scripting (XSS). XSS is a type of attack where malicious scripts are injected into trusted websites. For example, an attacker can sent malicious code to an end users and when the script gets executed, a range of  script-specific hacks could be performed.

4.

Changing the trust a Site is linked to on the Site reference table on the FE does not cause the Trust ID to be updated (Ola)

Before Fix

Site Creation: https://www.loom.com/share/2f1e398ea6d54d5c9780f1208c30fd3e

Site Updating: https://www.loom.com/share/55c0b78e3e5340b0a97f2770070528cf


After Fix

Site Creation: https://www.loom.com/share/afd2db8829414288b3f7196730fdbef3

Site Updating: https://www.loom.com/share/b806baf461fb438dbbdc398477829fc4

5.

Replace backend query param sanitizer 

TCS Jayanta Saha

Bulk Upload Yafang Deng

Assessment Yafang Deng

Before Fix

https://www.loom.com/share/005de071336a40e3be17d5795c909b5c

6.Portsmouth NHS Trust applicants for August 2019 Rotations not exported (??)
7.ESR - Investigate on having Monitoring for the FTP uploads and downloads failures on N3 (??)
8.Service Status (Abrar and Pete)



Stakeholders / Users invited to query / interrogate / applaud (after Sprint Review POs convert consensus inputs into backlog tickets, giving the option to consider them in the coming Sprint Planning)



POs present the roadmap