This was a 4-week Sprint to account for Christmas Day and New Years Day falling on Wednesdays, throwing our normal Sprint schedule out.

PO present a review of Sprint goals and other committed work



Sprint Goal

  • Integrate TIS updates into the ESR app generation & break new ground in bi-directional
  • Plan the change of hosting from Azure to AWS and develop the initial building blocks to enable Trainee UI development in January/February
  • Have a merry Christmas and support Pete and Abrar to finish their 2nd project



POs supported by Dev team provide a narrative on why, and what, emergency work was brought into the Sprint and which committed-to tickets were moved out as a result


Live Issues:

Jira Legacy
serverSystem JIRA
columnstype,summary,story points (effort),assignee,created,status
maximumIssues20
jqlQueryproject = TISNEW AND issuetype in (LiveDefect, Support) AND Sprint = 276 order by created DESC
serverId4c843cd5-e5a9-329d-ae88-66091fcfe3c7


Sprint Challenges 



Dev team demo 'done' work contributing to those goals
(no reference to specific Jira tickets, and no reference to work not 'done')

ItemDemo - from Prod URL where feasible
Demo #Area
1TIS ADMIN UI

Remove Inactive values from filters on Person and Post list pages

 - Person list

  • Placement grade
  • Placement speciality
  • Site
  • Placement type

- Post list

  • Primary site
  • Approved grade
  • Primary speciality
  • Programme name

Jira Legacy
serverSystem JIRA
serverId4c843cd5-e5a9-329d-ae88-66091fcfe3c7
keyTISNEW-3435

Babul Reddy Yasa (Unlicensed) from Prod
2ESR

Sachin - ASG Split (BI Directional)

David - CSV Validation

          - Marking App Records as exported

Paul   - Unhappy path of reconciliation & app generation

Phil   - Python & Neo4J auditing

         - Support of Legacy system

The Plan

Where we were at the end of sprint 7


Where we are now

Placement Lifecycle state

https://www.loom.com/share/a6a4cb8690b940bca4b45e8e9f2e7ee4


3TRAINEE-UICreate skeleton service for trainee ui

Backend tech and api Discussion plus Swagger Demo @Jayanta

Front End Demo

4ADMINS-UI

Improve the functionality of the PPT Approve All button

Get some feedback on changes made. They haven't been pushed to prod yet as we need to upgrade Angular version first (we found this out mid sprint!).

(Live demo)

5


6


7


8








Stakeholders / Users invited to query / interrogate / applaud (after Sprint Review POs convert consensus inputs into backlog tickets, giving the option to consider them in the coming Sprint Planning)



Sprint Goal (achieved? (thumbs up) / (thumbs down)): 

  • Integrate TIS updates into the ESR app generation & break new ground in bi-directional
  • Plan the change of hosting from Azure to AWS and develop the initial building blocks to enable Trainee UI development in January/February
  • Have a merry Christmas and support Pete and Abrar to finish their 2nd project



Current Priorities

- Overall and next sprint