ESR sent through a number of FULL FILES on 1st of March that did not load or fully load/reconcile to then send applicants against subsequently for St Helens & Knowsley Trust. This meant a delay in sending across Applicant Files to ESR.

ESR told us previously that the maximum number of full files they would send us was 3 per week. On Monday 1st of March, they sent through 9 files, 8 distinct with 1 duplicate.

...

Trigger

Unexpected number of FULL FILES (RMF) causing an overload on the TIS-ESR interface.

...

  • An issue raised on Teams regarding missing applicants from Liam Lofthouse (NWM Data Lead)

  • Image RemovedImage Added

...

Resolution

...

Timeline

...