Production Application releases / updates:


Releases

  • TIS-33 released to Stage and Prod - includes changes to reference service, tcs and assessments (server side)

Product Management

Assessments - Ran walk through with SMLs for the first iteration of Assessments in Prod. Period of testing and reviewing ongoing for SML call on Friday 2 Feb.


Oriel Integration

TISDEV - 3373, TISDEV - 3549, TISDEV - 3780, TISDEV - 3047, TISDEV - 2579


ESR Integration

  • Ongoing work for TIS to ESR Reference data/LOV alignment with National Workforce Dataset 2.8
  • 5 Notification types identified for Notifications Export. Victoria and Pavitra to send a list of scenarios and the corresponding combination of Notification Types expected for each in the Generic Inbound Notification File.
  • Solution design with Paul and Jag on how to stage the placement changes made on TIS


Document Management


Feedback from SMLs for components - Programmes, Posts, People, Placements, Assessments

  • stories/tasks/bugs have been discussed and prioritised with BMs 
  • sizing and priorities have been shared with Devs, prepped for development
  • online spreadsheet is being maintained to view these priorities and sizes (priorities also reflected in tickets on Jira as P1, P2 etc)
  • a number of these tickets are now in progress/complete
  • Basic requirements for Search functionality in the four P components to be investigated by Amupama for dev and delivery into MVP.


NFR Development of Requirements

  • an overall summary of requirements has been drafted from a business perspective
  • shared with limited view until it's deemed "complete", currently under review with Ray/Chris
  • there are some outstanding questions which requirements are dependent on, so still needs work into the next sprint


Study Leave

  • Claire LeHoux reviewed the proposed study leave template  for LaSE for bulk import of study leave and expenses
  • Next steps to review the template along with the solution design for Absence on TIS


Trust UI - who and what do they need. Trust access is no longer in scope for delivery by end of March.

Matt: The following tickets are now in complete and have been added to the 'Design to Deevelopment' document that is released to Panos and Reuben at the start of each new Sprint (Sprint 42 next).

Admin UI: Abesnse in People - Done: TIS Admin - Absence in people: Viewing, creating and editing absences
Admin UI: Document Manager (in People): TIS Admin UI - Documents manager
Admin UI: Search (Smart) and Table content/functionality with in search: This is ongoing to sprint 42 with UX documentation for feedback from SML's
TIS Roadmap: This is for interanl documentation for NHS/stakeholders - Done: TIS Concepts

Reporting - local offices have been given Tableau credentials and are testing/reviewing the reports created by Alice and James. Feedback being gathered on Teams


DevOps

MVP analysis for DevOps


Elastic Search fixes to support delta endpoints


Pipeline for Intrepid ETL to build Mirror from DR V2


Blue/Green improvements


Azure rolling upgrades to support


Sandbox Environment for better dovops testing without impacting dev environment


Storage Accounts have been migrated from the old TIS subscription to the Production subscription 


TIS Core Services Alpha build

Assessments

  • Outcomes - View completed (Create/View/Update) and validation work based on scenarios implemented
  • Revalidation - View completed (Create/View/Update) and validation work implemented
  • Unit test WIP

People - cache refresh solution design and implement


ETL review - what, where, when


ETL - Posts to new ETL structure, Consolidated ETL rationalise and implement scheduled


Bulk upload for People


Delta endpoints for large objects


Revalidation ETL - migrate to Mirror


Defects on People, Posts in particular


Extending E2E testing coverage

  1. Review and update existing E2E tests for different components (TISDEV-3496)
  2. Review e2e test coverage for different components and create e2e test coverage document on confluence (TISDEV-3745)
  3. Debug and fix protractor config or flaky E2E process (TISDEV-3307)
  4. Run E2E test pack against staging manually
ESR IntegrationFormer user (Deleted)
Oriel IntegrationSunil Rochani (Unlicensed)
Data Quality

Data_quality colleagues

Data quality issues with respect to People and Posts

Resource Planning

Reuben Noot (Deactivated)

Andy Nash (Unlicensed)

Agency update

  • Welcome to our new Front End Developer - Former user (Deleted)!
  • Also the new DBA, ??? (Kais' replacement), started in the NDW team this week.

Full Time recruitment

  • Roles advertised. Agency's approached. Interest: 
  • Also Michelle Hanson (the BA James recruited, who has now since left) reviewed the job descriptions HEE send out for the Full Stack and Front End Developer roles with Andy Nash (Unlicensed) and Simon Meredith (Unlicensed) which has now been passed onto James. Hopefully, the result will be that these can be adopted in future (2 pages written in a way that targets devs, rather than 13 that is a more standard HEE marketing-led officialese JD!).

...