Background
The scope of TIS was developed in 2015 through a requirements gathering process that involved all teams. A lot has happened since 2015, so we need to re-verify what we understand to be TIS. This will help us plan the future objectively. Part of the future planning will be process alignment, so that when we start to look at new developments we do so with assurance that we have already agreed a standard approach.
...
Attendees
Morning session - High priority components
...
# | Component (in no particular order) | High level requirements (from most to least no. of BV 1s by component) | Jira Story |
---|---|---|---|
1 | F09 – Trainer user interface (portal) and management |
|
...
| |||
2 | F02 – Assessment |
| |
3 | F20 – Reporting and analytics |
| |
4 | F05 – Course and event management (including study leave) - (classed as in between M/H) |
| |
5 | F12 – Post management |
| |
6 | F17 – Trust Access |
| |
7 | F08 – Trainee Access |
|
Additional notes:
- Reference tables management raised as an issue to be addressed
- Show & Tell - Priority of requirements to be raised with Business Managers and Show & Tell, or speaking to Rob Pink.
- Priority of new developments against stabilisation of existing functionality was raised. Upon discussion, only 1 person found it of a priority to prioritise stabilisation over new developments.
Case Study - Post Funding, work to address Post Funding:
- Settled on when trying to work out a Post occupancy report
- Revealed Inconsistencies in Data due to variation in practice across teams.
- Invlove National Finance to get their steer
Afternoon session - Process Alignment notes:
Interim Assessments
- Recording of PYAs - process for recording this on TIS requires alignment (Joanne Watson (Unlicensed))
- Terminology alignment and National Taxonomy definition for TIS
- Recording of Interim Assessments v.s. Educational reviews
- Do we need to record Interim type?
- Interim assessment is an assessment but an event and should ideally be part of event recording
- Agreement by the audience was - Do not record interim reviews.
- SOP to be reviewed to reflect these and communicated. Sharepoint to be updated.
- Educate Local area staffs on Procedures
- API - Integration with E-portfolio, this required data sets to be analysed and agreed as a Longer term piece of work to avoid duplication of work in recording assessment. Link to share information.
...