Morning session - High priority components
# | Component (in no particular order) | High level requirements (from most to least no. of BV 1s by component) | Jira Story |
---|---|---|---|
1 | F09 – Trainer user interface (portal) and management |
| |
2 | F02 – Assessment |
| |
3 | F20 – Reporting and analytics |
| |
4 | F05 – Course and event management (including study leave) - (classed as in between M/H) |
| |
5 | F12 – Post management |
| |
6 | F17 – Trust Access |
| |
7 | F08 – Trainee Access |
|
Additional notes:
- Reference tables management raised as an issue to be addressed
- Show & Tell - Priority of requirements to be raised with Business Managers and Show & Tell, or speaking to Rob Pink.
- Priority of new developments against stabilisation of existing functionality was raised. Upon discussion, only 1 person found it of a priority to prioritise stabilisation over new developments.
Case Study - Post Funding, work to address Post Funding:
- Settled on when trying to work out a Post occupancy report
- Revealed Inconsistencies in Data due to variation in practice across teams.
- Invlove National Finance to get their steer
Afternoon session - Process Alignment notes
...
Interim Assessments
- Recording of PYAs - process for recording this on TIS requires alignment (Joanne Watson (Unlicensed))
- Terminology alignment and National Taxonomy definition for TIS
- Recording of Interim Assessments v.s. Educational reviews
- Do we need to record Interim type?
- Interim assessment is an assessment but an event and should ideally be part of event recording
- Agreement by the audience was - Do not record interim reviews.
- SOP to be reviewed to reflect these and communicated. Sharepoint to be updated.
- Educate Local area staffs on Procedures
- API - Integration with E-portfolio, this required data sets to be analysed and agreed as a Longer term piece of work to avoid duplication of work in recording assessment. Link to share information.
...