(assume Team Availability Calendar is up to date, otherwise, everyone was available for 10 days of the Sprint, minus Bank Holidays and the Hack day 2018-12-14)
Full team availability 10 day Sprint * 13 dev team members | 130 days |
---|---|
Ashley Joanne Matt Chris John Jay Ola Paul Shivani Simon | -9 days -4 days -2 days -5 days -5 days -1 days -4 days -6 days -4 days -7 days |
Total team absence | -47 days |
...
Sprint Priorities
The following list was the prioritisation output from Sprint Planning - largely a stabilisation Sprint:
...
Item | TIS Ref / Owner | Status | Description of work | Link. e.g. to working software https://apps.tis.nhs.uk/ (note: use Dev for obfuscated data) Loom video of completed work https://www.useloom.com/ | |||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| |||||||||||||||||
Technical debt & Non-functional requirements: | |||||||||||||||||
Knowledge transfer: | |||||||||||||||||
|
| Ongoing Making some progress - but still migrating... | |||||||||||||||
Resource Planning: | Simon has now gone on Paternity leave - due back 2018-04-29. Ongoing recruitment push:
|