Availability

...

(assume Team Availability Calendar is up to date, otherwise, everyone was available for 10 9 days of the Sprint, minus Bank Holidays and the Hack day 2018-12-14)

Full team availability 10 9-day Sprint * 13 dev team members130 117 days

Ashley

Joanne

Matt

Chris

John

Jay

Ola

Paul

Shivani

Simon

-9 -2 days

-4 2 days

-2 days

-5 days

-5 days

-1 days

-4 days

-6 days

-4 days

-7 days

Total team absence-47 6 days



...

Sprint Priorities

The following list was the prioritisation output from Sprint Planning - largely a stabilisation Sprint:

  1. MVP for the Progress towards delivery of Placement Planning Tool MVP
  2. Resolving issues requiring lots of manual intervention on site reference tables
  3. Kubernetes migration and team education
  4. Elastic Search upgrade
  5. Finishing off some data cleansing
  6. Extend E2E tests for Bulk upload (Placements)
  7. Continue rolling out upgraded Elastic Search service


...

Contents

The following items to be shared by team members during this sprint review

Simon has now gone on Paternity leave - due back 2018-04-29.

Item

TIS Ref / Owner

Status

Description of work

Link. e.g. to working software https://apps.tis.nhs.uk/
(note: use Dev for obfuscated data)
Loom video of completed work https://www.useloom.com/

Jira Legacy
serverSystem JIRA
columnskey,summary,type,assignee,status,business value,story points (effort),priority (bv*sp)
maximumIssues100
jqlQueryproject = tisnew AND type not in (Sub-task, Epic) AND (assignee not in (benjamin.witton, Chris.Norman, Nazia.Akhtar, david.short, james.harris) OR assignee is EMPTY) AND sprint="Sprint 6465" ORDER BY status DESC, assignee ASC, cf[11231] ASC, cf[11233] ASC, cf[11237] ASC
serverId4c843cd5-e5a9-329d-ae88-66091fcfe3c7

Technical debt & Non-functional requirements:











Knowledge transfer:

  1. Confluence housekeeping - especially deleting documentation that is out of date. Ongoing
  2. Dev standards (Dev meeting / series of meetings). Ongoing
  3. Pairing / Mobbing
  4. Git-commit messages
  5. Walk-throughs (prep as you go - links?). 
  6. Architectural level diagrams
  1. Andy Nash (Unlicensed)


  2. All Dev team
  3. All Dev team
  4. All Dev team
  5. All Dev team
  6. All Dev team

Ongoing














Resource Planning:

Andy Nash (Unlicensed)Eniola Agbeti (Unlicensed)


Ongoing recruitment push:

  • in Manchester: SM, UX/UI, LD, 2*Dev 2*apprentice devs
  • and London: DevOps, 2*Dev, 2*Dev DOS contractors

...