Availability
(assume Team Availability Calendar is up to date, otherwise, everyone is available for 8 days, as this Sprint contains a Bank Holiday):9 days):
Sunil Fred Ola Simon Andy Matt Joanne Chris | -2 -2 -2 -1 -2.5 -2 -1 -2 |
---|
...
Sprint Priorities
The following list was the prioritisation output from Sprint Planning - largely a stabilisation Sprint:
...
Item | TIS Ref / Owner | Status | Description of work | Link. e.g. to working software https://apps.tis.nhs.uk/ (note: use Dev for obfuscated data) Loom video of completed work https://www.useloom.com/ |
---|
Production Application releases / updates | Simon Meredith (Unlicensed) Oladimeji Onalaja (Unlicensed) Jayanta Saha John Simmons (Deactivated) Shivani Rana (Unlicensed) (and anyone else involved) | Release 58a | Bugs - Programme membership info not showing correctly
- GMC sync failure investigation (incl RCA) - develop actions to mitigate future failure
- Programme memberships now longer displaying in chronological order
- Fix the HATEOAS pagination of posts on backend
Stories - User/Application Database access restriction
- Bulk Upload/Create Assessment events
- Create Read only role for trust users
- Amend current Trust access role
- User Management - Create "read journey" for current users
|
|
|
|
|
|
|
Jira Legacy |
---|
server | System JIRA |
---|
columns | key,summary,type,assignee,status,business value,story points (effort),priority (bv*sp) |
---|
maximumIssues | 100 |
---|
jqlQuery | project = tisnew AND type not in (Sub-task, Epic) AND assignee not in (benjamin.witton, Chris.Norman, Nazia.Akhtar, david.short, james.harris) AND sprint in openSprints (97) ORDER BY status DESC, assignee ASC, cf[11231] ASC, cf[11233] ASC, cf[11237] ASC |
---|
serverId | 4c843cd5-e5a9-329d-ae88-66091fcfe3c7 |
---|
|
|
|
|
|
|
|
Technical debt & Non-functional requirements: |
Admins UI security vulnerabilities in dependencies |
|
|
|
|
|
|
|
|
|
|
Knowledge transfer: |
- Confluence housekeeping - especially deleting documentation that is out of date. Ongoing
- Dev standards (Dev meeting / series of meetings). Ongoing
- Pairing / Mobbing
- Git-commit messages
- Walk-throughs (prep as you go - links?).
- Architectural level diagrams
| - Andy Nash (Unlicensed)
- All Dev team
Paul Hoang (Unlicensed) leading - All Dev team
- All Dev team
- All Dev team
- All Dev team
| Ongoing | Making some progress - but long way still to go... |
|
|
|
|
|
|
Resource Planning: | Andy Nash (Unlicensed) Eniola Agbeti (Unlicensed) |
| TIS Team #2 recruitment ongoing. Interviews taking place this Thursday / Friday in Manchester for UI/UX and Scrum Master. This Sprint we said goodbye to Sunil and Fred. |
|
...