Status | Work area | Date | Description | ||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Reval Connections MVP8-20 Iterations |
|
| ||||||||||||
| TIS Self-Service MVP1 Iteration left |
| First cohort of Trainees (c.50, from across LOs, all of whom will be at the point of needing to fill in their Form Rs imminently):
HEE Admin:
2021-04-14 - Outstanding estimate of a few days, before doing some live run throughs and quick fixes, before starting the Pilot. 2021-01-08 - Original estimation: 3-4 iterations (mid-Feb --> Mid-Mar) 2021-02-05 - Progress and revised estimation: (1st → 3rd week in March) 2021-02-12 - 4/5 confidence estimate still holds 2021-02-22 - Updated. Behind due to sync service speed issues, interruptions (live defects and other essential TIS/ESR Work) and holidays. 2021-03-05 - Updated. Resolved majority of performance issues. Back to a 1-2 Iterations remaining estimate. 2021-03-17 - Updated. Tidying up sync stuff, and address TISSS Feedback tickets in Backlog/Refinement | ||||||||||||
| NIMDTA TIS MVP |
| All requested Intrepid NIMDTA admins users onboarded on, and are administering Trainees within NI exclusively from the NIMDTA TIS app, the NIMDTA Intrepid app is read-only and can be switched off. NIMDTA Admins' Administration of Trainees includes:
HEE Admins will also be able to:
(Note: for MVP, real-time data synchronisation between TIS and NIMDTA TIS is not yet in place) Data sync of person details | ||||||||||||
| Reval MVP |
| Operations & Access
Application
2021-04-16 - Updated estimate range (optimistic → pessimistic) of what has been requested 13-23 Iterations (6-12 months). |
...