Availability
(assume Team Availability Calendar is up to date, otherwise, everyone is available for 12 days: 3 week Sprint, but with 2 Bank Holidays):
Andy | -5 -1 -8 -6 -1 -1 -1 -4 -6 |
---|
Sprint Priorities
The following list was the prioritisation output from Sprint Planning:
Product Management
Developer Support
- Bulk upload / ESR support and integration testing
North East team support
Prep for remaining roll-out
- Prioritisation of P1s and others (including Rotations - especially for London)
- Relative prioritisation between live feedback and planned development
Development
4Ps and A
- Stability of NE - triage and fix
- P1s for other LOs - PO Group to keep under review
- Testing of P1s - updating tests and retesting - continuing with automation of tests
TIS → NDW ETL
- TIS data is in tis_interim for further processing.
- Support NDW if there are questions regarding the mapping.
ESR
- Infrastructure set up for ESR and ESR-ETL services to work with tcs.
- And make the services deployed and available in Dev/Stage and Prod.
- Initiate the testing on Stage.
Bulk upload
- Suneet Kamath (Unlicensed) - update please
Frontend
- Bug fixes on displaying errors
- Now supports placements (changes icon and provides template)
- Templates now stored in Azure bucket rather than in codebase
Document management
Backend API has now support for
- Searching tags
- Download documents
Frontend changes
- Now handles all API errors
- Some test coverage (needs more)
- Downloads section placed into the person section dropdown
- Searching with changes now shows confirmation prompt
- Delete file requires confirmation using new modal component
- Navigating away with unsaved changs shows unsaved prompt
- Shows CSS loader animation when fetching data
- Uses Bootstrap date picker
- UI tweaks to make list a little clearer
User Management
- Simon Meredith (Unlicensed) - update please
Reval
- Sunil Rochani (Unlicensed) - update please
DevOps
- Frederic Randriamora (Unlicensed) / John Simmons (Deactivated)
- Document Storage Chris Mills (Unlicensed)
- Terraform now modular, repeatable and secure.
Data
- Can we get DQ leads to do a more thorough review?
Contents
The following items to be shared by team members during this sprint review
Item | Owner | Description of work | Link to working software https://apps.tis.nhs.uk/ (note: use Dev for obfuscated data) | Loom video of completed work https://www.useloom.com/ |
---|---|---|---|---|
Production Application releases / updates: | Oladimeji Onalaja (Unlicensed) (and anyone else that needs to conduct a release) | Releases75 tickets moved to 'Ready to Release' or 'Done' in this sprint: | ||
Product Management | Analysis and refinement:
Developer support:
North East Support:Prep for remaining rollout: Rotations UX/UI: Matt TIS Admin UI - Removing items and user feedback: TIS Admin UI - Programmes in People - Removing a programme and user feedback TIS Admin UI Enhancement - UI background and section containers: TIS Admin UI - UI Enhancement - UI background and section containers TIS User Guide: TIS Admin UI User Guide TIS Design to development pre Sketch: TIS Design to development - Post April 2018 - Design files and dev notes | |||
DevOps | Chris:
| |||
TIS Core Services: Back end | Post to Programme many to many
Rotations TIS-NDW ETL
Consolidated DR ETL
Bulk Uploads - People and Placements Reference data refresh Back end field validation improvements Revalidation converted to work against TIS rather than Intrepid | |||
TIS Core Services: Front end | Bulk Uploads Document Management
Multi-Select Widget - Person:Roles
New Dropdowns NPN feedback to user following Post creation Panos | |||
ESR Integration | ||||
Data Quality | Data_quality colleagues | |||
Resource Planning | Agency update Full Time recruitment |
Add Comment