Availability

(assume everyone is available for 9 days, except the following):

Christmas period - almost everyone had some time off.

Assume this 3 week Sprint equated to a standard 2 week Sprint as a result.



Sprint Priorities

The following list was the prioritisation output from Sprint Planning:

Product Management

Developer Support

  • Assessments - Outcomes and Reasons, Revalidations
  • Other - dependent on Dev prioritie

Analysis and refinement

  • SML/Trainee Review coordination (Assessments, People, Posts, Placements, Trainee UI)
  • Admin UM - Role definition
  • PersonAssociated... review
  • Reporting - review first 10 reports from NDW team, SML's given access to Tableau
  • Oriel Integration - definition of the Oriel Custom report, Recruitment Import template, data quality issues
  • Bulk uploads - story refinement
  • Hicom Procurement review
  • Supporting Data Leads

Development

  • Placements - Unit Test coverage and release to Production
  • Assessments - ETL for Revalidations, Service and UI for Revalidations, Person view of Assessment
  • People - ETL and data model refactoring for performance and stability, PersonOwner blocked by ProgrammeMembership ETL issue
  • Bulk Upload - design review on how to plumb in the UI - asynchronous?
  • ESR Integration - continuing refining the APP file, including DR2 fields, Notification service
  • Admin UM - change admin user details, complete solution design
  • TIS-NDW ETL - start development

DevOps

  • Finalise UAT Environment
  • Update documentation, code and diagrams for better onboarding
  • MySQL Managed within Azure

Data



Contents

The following items to be shared by team members during this sprint review


Item

Owner

Link

Production Application releases / updates:


Releases


Product Management

Bulk uploads -

  • Stories added and refined for Absence, People, NTN Assignment, Posts, Placements. Assessment events and ARCP still need to be reviewed. 


Assessments -

  • List of outcomes for ARCPs agreed by SMLs and written into story  (for action in Sprint 40). 


Oriel Integration -

  • TIS Recruitment Import template refined with feedback received from Alice and Claire. There are still some outstanding questions on some fields.
  • Definition of the Oriel Custom report meeting kicking off on Thursday 04/01 with Claire.


ESR Integration -

  • Analysis of the ESR documentation completed. Followed up queries with VH. Produced the following workflow as an initial understanding of the ESR inbound/outbound flows
  • Outstanding questions (contextual) to be followed up with Wendy Burney from NE on 03/01.
  • TIS/ESR reference mapping done but still has some outstanding queries sent to VH to be clarified. Some LOV's were not present in the documentation and some with no values to map to.
  • Channel created on Microsoft Teams for the discussion of the ESR interface and the Streamlining programme.
  • Summary of process to be followed to set up a Trust with the interface posted in the channel to support those local offices with new trusts needing to use the interface.


Reporting -

  • First batch of required reports forwarded to Alice Brindle and James Harris for creation in the NDW. 


Trust UI - 

  • Proposed familiarisation and roll out plan for trust users forwarded to Angela Fletcher (component lead BM) for review and follow up


Absence -


PersonAssociated

  • stories completed w/scenarios and field validation for Trainer Person views
  • still to be finally reviewed with SMLs (post Christmas)


Admin UM

  • role definitin and permissions continued, finalisation TBC


Misc

  • Update the TIS services to allow clients (Datawarehouse, external services) to retrieve data that have been modified in TIS
  • Initial work to bring in service contracts using Pacts
Intrepid Data QualityRussell Steel (Unlicensed)


TIS Core Services Alpha build

Admin UI

Programmes

People

Alex Dobre (Unlicensed) to update with People etl changes and performance updates to the view

Posts

Placements

Assessments

  • Assessment List per trainee via a new Assessment section in People View has been implemented - List has been linked to main Assessment entity.
  • Final assessment sub-section 'Revalidation' has been added to the Assessment entity - Create/Update functionality implemented.
  • Tests and hardening on the Assessments
  • Initial work on Service Pacts

User Management

Roles/Permissions in Dev, Stage and Prod in sync

Trainee UI


Intrepid Mirror



Intrepid DR v2

Graham O'Regan (Unlicensed)

Russell Steel (Unlicensed)

Sunil Rochani (Unlicensed)

  • Database structure changes to support DR v2 and sync DR v2 and mirror 
Intrepid ETLs

Graham O'Regan (Unlicensed)

Chris Mills (Unlicensed) 

Paul Hoang (Unlicensed)

Russell Steel (Unlicensed)

  • Updates to ETL to bring in Assessment Outcomes and Revalidations
Oriel Integration 

Graham O'Regan (Unlicensed)

Sunil Rochani (Unlicensed)

  • Initial Oriel intregration to import Oriel xml files  
ESR Integration
  • Initial LOV mappings are done and still there are gaps in the mappings which are being worked out.
  • Incorporated the available LOV code for Applicant File generation. There are still gaps because of the above.
  • Validation Issues related to skipping the records without mandatory fields are fixed. (DOB, address line 1 etc). The data quality should be resolved over time to minimise such records. 
  • Code refactoring and code coverage is in progress.  
DevOps

Chris

  • UAT Environment
  • Able to run ansible playbooks locally in vagrant
  • Added flight rules
  • Initial Pact Broker implementation
  • Moved to using JDK rather than JRE, gives support for forcing dump etc
  • Minor patches and better control over peroidic security patches

Frederic

  • Vagrant box for UIDEV; code needs to be merged

John

  • Moving plain text passwords to vault and updating associated playbooks
  • Creating a keycloak admin password rotation playbook
  • Occational user support requests
Resource Planning

Reuben Noot (Deactivated)

Andy Nash (Unlicensed)

Full Time recruitment

  • Full Stack Dev and Front End Dev re-advertised. 18 applications through Trac. Simon and Reuben are shortlisting.

Agency update

  • Graham, Steve and Russ all left us just before Christmas (sad)
  • Alex will be leaving us at the end of this week (sad)
  • Reuben was able to source 3 new developers from Transform in place of (not replacements for!) Alex and Graham.
    Welcome to: Andras Bulla, Luis Matos and Suneet Kamath (smile)
  • Andy and Eniola attempting to source 2 more developers through agencies. No joy as of yet. Christmas break has made most agencies totally unresponsive!
 User ResearchAnupama Roy (Unlicensed)

Planned work with UX

  • List UR questions @ AR & ML
  • Digital accessible stats/list @AR
  • Mapping TIS components and user journeys using Invision @AR &ML
  • Involve Matt in user testing, journey mapping
  • Send mailing lists & slack link to Matt about GDS & UR

Planned work with BA on SML feedback processes

  • Take over feedback and responding process to SML from Ify.
  • Arrange weekly meetings to go through the process with BAs, POs & SMLs
  • Report any challenges in the process with managing UR work

Familiarising with TIS test environment with Simon

  • Learnt log in process
  • Skimmed through the environment