Availability
(assume Team Availability Calendar is up to date, otherwise, everyone is available for 9 days):
Joanne Jayanta John Andy Panos Ray Ashley Sunil Transform | -1 -8 -2 -0.5 -7 -3 -2 -2 -36 |
---|
Sprint Priorities
The following list was the prioritisation output from Sprint Planning - largely a stabilisation Sprint:
- Completing left-overs from Sprint 54
- Reval stabilisation
- New pipeline/K8s/infrastructure
- Trust UI MVP scoping
- Document Manager
Contents
The following items to be shared by team members during this sprint review
Item | TIS Ref / Owner | Status | Description of work | Link. e.g. to working software https://apps.tis.nhs.uk/ (note: use Dev for obfuscated data) Loom video of completed work https://www.useloom.com/ | |
---|---|---|---|---|---|
Production Application releases / updates | Oladimeji Onalaja (Unlicensed) (and anyone else involved) | ||||
Technical debt & Non-functional requirements: | |||||
Admins UI security vulnerabilities in dependencies | |||||
Knowledge transfer: | |||||
|
| ||||
Resource Planning: | BA recruited: Starting today. Welcome Tayo Okuyedi |