Availability (note Sprint 64 is a 3-week Sprint because of Christmas)
(assume Team Availability Calendar is up to date, otherwise, everyone was available for 10 days of the Sprint, minus Bank Holidays and the Hack day 2018-12-14)
Full team availability 10 day Sprint * 13 dev team members | 130 days |
---|---|
Ashley Joanne Matt Chris John Jay Ola Paul Shivani Simon | -9 days -4 days -2 days -5 days -5 days -1 days -4 days -6 days -4 days -7 days |
Total team absence | -47 days |
Sprint Priorities
The following list was the prioritisation output from Sprint Planning - largely a stabilisation Sprint:
- MVP for the Placement Planning Tool
- Kubernetes migration and team education
- Elastic Search upgrade
- Finishing off some data cleansing
Contents
The following items to be shared by team members during this sprint review
Item | TIS Ref / Owner | Status | Description of work | Link. e.g. to working software https://apps.tis.nhs.uk/ (note: use Dev for obfuscated data) Loom video of completed work https://www.useloom.com/ | |
---|---|---|---|---|---|
| |||||
Technical debt & Non-functional requirements: | |||||
Knowledge transfer: | |||||
|
| Ongoing | |||
Resource Planning: | Simon has now gone on Paternity leave - due back 2018-04-29. Ongoing recruitment push:
|