2021/2: Q2 | Review#4 (2021-08-03 to 2021-08-17)

Welcome

  • Overviews of the iteration

  • Any interruptions / Live Defects

  • Team going through what they’ve achieved during the iteration

  • Feedback from those on the call on what we have done (constructive criticism / praise / questions)

  • Collaboration with those on the call on what to do next

  • Ask questions:

- out loud on the call - really, we’d appreciate you doing this!;
- write in the Team meeting chat; or
- fill in the post-Review survey after the call
(for questions that occur after the call is over, or if you don’t want to ask the question during the call for whatever reason, and
for letting us know whether the Review meets your expectations, or whether you have some suggestions for improvement)

  • Overviews of the iteration

  • Any interruptions / Live Defects

  • Team going through what they’ve achieved during the iteration

  • Feedback from those on the call on what we have done (constructive criticism / praise / questions)

  • Collaboration with those on the call on what to do next

  • Ask questions:

- out loud on the call - really, we’d appreciate you doing this!;
- write in the Team meeting chat; or
- fill in the post-Review survey after the call
(for questions that occur after the call is over, or if you don’t want to ask the question during the call for whatever reason, and
for letting us know whether the Review meets your expectations, or whether you have some suggestions for improvement)

Live Issues:

key summary created updated status
Loading...
Refresh

 

Incident logs

Initiated last iteration, ongoing

2021-08-02 Placements not being exported to ESR

Initiated last iteration, completed this iteration

2021-07-30 Old RabbitMQ prod broker deleted before the EsrDataExport service was moved to new RabbitMQ broker

2021-07-23 NIMDTA TIS-NDW ETL failure

Dev team demo 'done' work contributing to those goals (no reference to specific Jira tickets, and no reference to work not 'done')

Area

Description

Team Representative

Demo - from Prod URL where feasible

Area

Description

Team Representative

Demo - from Prod URL where feasible

TISSS

Add filtering for the list of subspecialties in the Form R Part A Declarations Section

@Edward Barclay

Reval

Historical data migration ETL

@Doris.Wong

 

Fixed typo when saving a recommendation

@Andy Dingley

Previous text:

Current text:

TIS / ESR

Validation for creation of current Trusts

@Andy Dingley @Marcello Fabbri (Unlicensed)

Demo from stage (change trustCode from ‘204’ to ‘15E’ and watch it not save)

Relax work email validation (controlled by ESR)

@Joseph (Pepe) Kelly @Reuben Roberts

https://www.loom.com/share/6cf5ebc53fad4f2b8c3fa842f43b22c9

https://stage-apps.tis.nhs.uk/admin/people/person/4194/edit-personal-details

Placement’s ESR export status accuracy corrected

@Marcello Fabbri (Unlicensed)

The ESR interface exported some placements but could not update their esr export status on TIS due to a live defect from the previous iteration. These placements have been manually updated to reflect the their successful export.

NIMDTA

 

 

 

 

 

 

Objective Key Results (OKRs) 2021/22 Q2:

OKR

1st
Iteration

2nd
Iteration

3rd
Iteration

4th
Iteration

5th
Iteration

6th
Iteration

7th
Iteration

Objective: Solve MFA and complete second live pilot

Key Result#1: Run an experiment with existing pilot Trainees on using an Authenticator App. Get sufficient feedback to develop it into a solution for the next pilot.

Too early to score

0.1

0.5

0.6

 

 

 

Key Result#2: Coordinate a 2nd pilot (confirm with teams running ARCPs - ask monthly. Any number would be insightful, ideally between 30-50).

Too early to score

0.1

0.1

0.2

 

 

 

Key Result#3: Run the 2nd pilot to include live ARCP Form R completion via the app (with associated HEE admin unlocking of Form Rs submitted in error, if needed).

Too early to score

0.1

0.1

0.1

 

 

 

Key Result#4: Ensure data from all fields in Form R is stored in a format enabling it to be extracted on demand for the purposes of reporting.

Too early to score

0.5

0.6

0.6

 

 

 

TIS Dev team roadmap:

Feedback

We really do welcome any feedback you have for us - whether it be negative or positive, or whether it be a suggestion of something we could try/incorporate in a future Review. We absolutely don’t want to stand still. We’re very happy applying the 12th Agile principle of ‘becoming more productive’ to our Reviews themselves! Your contributions to this survey are entirely anonymous, should you wish to include anything others might perceive as controversial. We welcome any and all feedback, as long as it is constructive!