Sprint 74 Review (2019-05-28)
Availability
(assume Team Availability Calendar is up to date, otherwise, everyone was available for 7.5 days (1 Bank holiday) of the 2-week Sprint)
Full team availability 7.5-day Sprint * 8 dev team members | 60 days |
---|---|
Andy, Yafang, JohnO, Simon, Ola, Jay, Pepe, John | |
Total team availability this Sprint | 79% |
POs present a review of Sprint goals and other committed work |
---|
Sprint Goal: | |
---|---|
Major improvements to ESR
|
POs supported by Dev team provide narrative on why, and what, emergency work was brought into the Sprint and which committed-to tickets were moved out as a result |
---|
Dev team demo 'done' work contributing to those goals (no more reference to specific list of Jira tickets, and no more reference to work not 'done') |
---|
Item | Demo - from Prod URL were feasible | Demo link |
---|---|---|
1. | Users cannot search or filter on all trainees at their local office - Oladimeji Onalaja (Unlicensed) | - TISNEW-2993Getting issue details... STATUS 2019-05-17 Users cannot search or filter on all trainees at their local office |
2. | ESR - performance (SQL refactor) - Joseph (Pepe) Kelly | |
3. | ESR - No APP Files generated by the TIS-ESR ETL Oladimeji Onalaja (Unlicensed) | |
4. | ESR - Investigation on handling multiple applicants per deanery number in the DNF/C Files Jayanta Saha | |
5. | ESR - Daily Notifications Load for Large Numbers Andy Dingley | |
6. | ESR - ETL Notification date coverage john o | |
7. | TIS-ADMINS-UI - Security vulnerability Oladimeji Onalaja (Unlicensed) | |
8. | ESR Applicant Export Failure 21st May 5pm Joseph (Pepe) Kelly | |
9. | Sync Service Joseph (Pepe) Kelly |
Stakeholders / Users invited to query / interrogate / applaud (after Sprint Review POs convert consensus inputs into backlog tickets, giving the option to consider them in the coming Sprint Planning) |
---|
POs present the roadmap |
---|
Slack: https://hee-nhs-tis.slack.com/
Jira issues: https://hee-tis.atlassian.net/issues/?filter=14213