Skip to end of metadata
Go to start of metadata

You are viewing an old version of this page. View the current version.

Compare with Current View Page History

Version 1 Next »

Availability

(assume Team Availability Calendar is up to date, otherwise, everyone is available for 9 days):

Joanne

Jayanta

John

Andy

Panos

Ray

Ashley

Transform

-1

-8

-2

-0.5

-7

-3

-2

-36




Sprint Priorities

The following list was the prioritisation output from Sprint Planning - largely a stabilisation Sprint:

  1. Completing left-overs from Sprint 54
  2. Reval stabilisation
  3. New pipeline/K8s/infrastructure
  4. Trust UI MVP scoping
  5. Document Manager





Contents

The following items to be shared by team members during this sprint review



Item

TIS Ref / Owner

Status

Description of work

Link. e.g. to working software https://apps.tis.nhs.uk/
(note: use Dev for obfuscated data)
Loom video of completed work https://www.useloom.com/

Production Application releases / updates

Simon Meredith (Unlicensed)

Oladimeji Onalaja (Unlicensed)

Jayanta Saha

(and anyone else involved)










key summary type created updated due assignee reporter priority status
Loading...
Refresh






Technical debt & Non-functional requirements:

Admins UI security vulnerabilities in dependencies











Knowledge transfer:

  1. Confluence housekeeping - especially deleting documentation that is out of date. Ongoing
  2. Dev standards (Dev meeting / series of meetings). Ongoing
  3. Pairing / Mobbing
  4. Git-commit messages
  5. Walk-throughs (prep as you go - links?). 
  6. Architectural level diagrams
  1. Andy Nash (Unlicensed)

  2. All Dev team / Paul Hoang (Unlicensed) leading

  3. All Dev team
  4. All Dev team
  5. All Dev team
  6. All Dev team








Resource Planning:

Andy Nash (Unlicensed)


BA recruited: Starting today. Welcome Tayo Okuyedi




  • No labels