Availability
...
- Admin UI Smart search and Table structures for 3P's and Assessments based on UX feedback
- UX/UI Package (Tidying up the site with UI/UX quick wins to implement through ongoing development work)
- Programmes - Educational Groups (Trainers) Field Validation & Scenarios - Design work
- Programmes - Rotations Field Validation & Scenarios - Design work - Moved to sprint 43 as requires additional UX chat
- People - Trainer Record Associations - Design work - Moved to sprint 43 as requires additional UX chat
- SML feedback analysis parallel to UX work
- Notifications (UI)
- Topping and tailing user journey on Assessments (Not sure what this is, must be new)
Development
- 4Ps P1&2 issues (Paul & Panos, Ola/Simon)
- ETL productionising - (Sunil, Chris) Consolidated ETL (Mirror→TIS) defects from staging resolved, retested and scheduled in production - future increments of missing data where identified as P1s
- Bulk upload of people (JohnG & Suneet) (FE and BE this sprint)
-
ESR (Jag, Ashley) - ESR 'notifications' development, exception handling
-
TIS-NDW ETL (Andras) - Finish Assessments and move through all other objects - PPPP and reference data
-
Delta Service (Luis) (complete including validating Person and join table updates are audited - e.g. ProgrammeMembership)
- Document Store (JohnG and Luis) - FE and BE development - implementing agreed endpoints - metadata management, retrieve documents from Hicom and load into Azure
- Rebase - code hooks need adding to the new Consolidated ETL and testing (Sunil / Paul?)
- Reval pulling from TIS, rather than Mirror (Sunil)
- Keycloak user permissions / roles / groups (Simon)
- E2E Assessment automation (Shivani)
- Extending E2E test coverage across other components (Shivani / Ola / Merce)
- Post list performance (Sunil) (replicate approach from People)
- Oriel Integration (Suneet) - following bulk person upload completion extend to support Oriel bulk import
...
Item | Owner | Link |
---|---|---|
Production Application releases / updates: | ReleasesKeycloak deployment on UAT, Live and Stage - reset password functionality added | |
Product Management | Developer supportAnalysis and refinementESR Integration:
Oriel Integration:
UX/UI
Workaround development
Admin UM
NE Implementation
| |
DevOps | UAT PenTest tasks Backups Elastic search: roll out the upgrade of spring boot for all the apps, then roll out the new version of ELK Jenkins Scaling Monitoring Bastion: New Vnet Configured to seperate bastion from jenkins, tested and working. Non default port used for SSH to try and make it a little more secure, when the new ssh config file is distributed i will remove the old access via jenkins. | |
TIS Core Services Alpha build | 4Ps P1&2 issues
Assessments
ETL productionising Post list performance TIS-NDW ETL
Delta Service
Oriel Integration Document Store
Bulk Uploads for People • UI is completed, final stage of integration with API in progress (almost ready to test) Rebase - code hooks Reval pulling from TIS, rather than Mirror Keycloak user permissions Extending E2E test coverage TISDEV-3981 (Update Programme E2E test cases due to changes in Create Programme UI) | |
ESR Integration | Former user (Deleted) | ESR
|
Oriel Integration | Bulk upload of people• UI is completed, final stage of integration with API in progress (almost ready to test) | |
Data Quality | Data_quality colleagues | Data quality support |
Resource Planning | Agency updateNo change. Full Time recruitment2 interviews lined up w/c 26/02. First one held and was a "No". More CVs being sent through for evaluation. |
...