(assume Team Availability Calendar is up to date, otherwise, everyone was available for 9 days)
Paul Simon Andy Shivani Joanne Roope Ben | -1 -3 -2 -1 -7 -1 -7 |
---|
Sprint Priorities
The following list was the prioritisation output from Sprint Planning - largely a stabilisation Sprint:
- Revalidation - code familiarisation, fixing bugs and preparing for upgrading the service
- Resolving NDW communication
- Preparing to develop an audit function
- Completing K8s service
- Complete User Management service
Contents
The following items to be shared by team members during this sprint review
Item | TIS Ref / Owner | Status | Description of work | Link. e.g. to working software https://apps.tis.nhs.uk/ (note: use Dev for obfuscated data) Loom video of completed work https://www.useloom.com/ |
---|
Production Application releases / updates | Chris Mills (Unlicensed) Simon Meredith (Unlicensed) Oladimeji Onalaja (Unlicensed) Jayanta Saha John Simmons (Deactivated) Shivani Rana (Unlicensed) (and anyone else involved) | Use of new release pipeline No specific release number | Bugs - Filtering on Funding Type error
- Post funding UI not appearing for some posts
- Cannot remove assessment outcome reason and save
Stories - Comments need to be surfaced in the NDW
- Add "missing" vwAssessments fields to NDW ETL
- Coordinate with Devops to include e2e tests run in release pipeline in staging
- Trust access to tableau - extra table needed in TIS NDW ETL
- POG Calculation for programme end date
- Invalid date formats not to be allowed by the generic uploads for Assessment
- Avoid all failing test in E2E test pack to avoid build failing
|
|
|
|
|
|
|
key |
summary |
type |
assignee |
status |
business value |
story points (effort) |
priority (bv*sp) |
|
|
|
|
|
|
Technical debt & Non-functional requirements: |
Admins UI security vulnerabilities in dependencies |
|
|
|
|
|
E2E testing |
|
|
|
|
|
|
|
|
|
|
Knowledge transfer: |
- Confluence housekeeping - especially deleting documentation that is out of date. Ongoing
- Dev standards (Dev meeting / series of meetings). Ongoing
- Pairing / Mobbing
- Git-commit messages
- Walk-throughs (prep as you go - links?).
- Architectural level diagrams
| - Andy Nash (Unlicensed)
- All Dev team
- Paul Hoang (Unlicensed) leading
- All Dev team
- All Dev team
- All Dev team
| Ongoing | Making some progress - but long way still to go... |
|
|
|
|
|
|
Resource Planning: | Andy Nash (Unlicensed) Eniola Agbeti (Unlicensed) |
| TIS Team #2 recruitment ongoing. Interviews took place in Manchester for UI/UX and Scrum Master. |
|