Skip to end of metadata
Go to start of metadata

You are viewing an old version of this page. View the current version.

Compare with Current View Page History

« Previous Version 6 Next »

Sprint goals review with team feedback

Sprint Goal

  • Make TIS Self Service accessible to users so we can get them involved with feedback.
  • Set up the Reval build environment to enable collaboration with Reval users throughout development.
  • Continue building out test environment for ESR Bi-Di and progress work on type 5 notifications.

Any live defects or interruptions? Any committed-to tickets were moved out as a result

Live Issues:

None

type summary story points (effort) assignee created status
Loading...
Refresh

.

Dev team demo 'done' work contributing to those goals (no reference to specific Jira tickets, and no reference to work not 'done')

AreaSquadWho's demoingDemo - from Prod URL where feasible

ESR:

  1. Existing system
  2. Bi-directional


ESRPhil James (Unlicensed)
  1. Where we were at the start of the Sprint
    1. Recap 
      1. Last sprint we Created the new Notifications service that would hold the new code that generates all notifications
      2. Fixed issues in the data exporter where sometimes the files weren't uploaded depending on which server that the job was running on
      3. Stabilised the Neo audit service
      4. Started work on getting atomic database and messaging actions
      5. Started work on extracting common code for easy re-use and time shaving 
  2. Where we are now
    1. Overview
      1. System now reacts to new Posts being created in TIS by creating Notification Type 5 (Post created) records
      2. Generalising data export code as there is a lot of shared functionality between App generation and Notifications
      3. Updated ALL of the Java based services to use the common code library, this gives all services the ability to send messages in a standard format AND apply rollbacks and retries when needed
    2. Things that are not quite ready
      1. BDD tests
      2. Database infrastructure for rollbacks

       

RevalidationRevalAndy Nash (Unlicensed)

Trainee-UI

TISLiban Hirey (Unlicensed)


Northern Ireland on-boardingTIS 

Jayanta Saha

 Babul.Yasa (Unlicensed)


SonarQube

TIS

Andy DingleySonar Demo

Priorities

  • Next Sprint
  • Overall
  • No labels

0 Comments

You are not logged in. Any changes you make will be marked as anonymous. You may want to Log In if you already have an account.