Availability
(assume Team Availability Calendar is up to date, otherwise, everyone is available for 8 days, as this Sprint contains a Bank Holiday):
Sprint Priorities
The following list was the prioritisation output from Sprint Planning - largely a stabilisation Sprint:
- Bulk Upload/Create Assessment events
Basically Done, in Dev. Discovered a blocker in Programme Memberships dependency (PM implemented too rapidly in the past and now needs refactoring).
Stabilised PM in order to enable completion of BU/A work (Create assessments only), but this necessitated significant change in Assessments, where some unit tests and possibly E2E tests are all that is now outstanding (Assessments will need some further refactoring in the future). - Manage Documents associated with a Person record
This ticket was not required once it was looked into - AKS Service on Azure
Team illness has prevented these tickets from being completed. Majority in place. Will need finishing off next Sprint. - Stabilise Reval
No Reval data in Dev, so Roope's progress has had to halt. Will bring data into Dev early in next Sprint.
Sonarcube threw up errors. These have now been dealt with. - Starting on Trusts
Ola presented new Trust Read only role and what they can and can't see. Amends made to the exiting Trust role to tweak what they can do.
Contents
The following items to be shared by team members during this sprint review
Item | TIS Ref / Owner | Status | Description of work | Link. e.g. to working software https://apps.tis.nhs.uk/ (note: use Dev for obfuscated data) Loom video of completed work https://www.useloom.com/ | |
---|---|---|---|---|---|
Production Application releases / updates | Oladimeji Onalaja (Unlicensed) (and anyone else involved) | ||||
Technical debt & Non-functional requirements: | |||||
Admins UI security vulnerabilities in dependencies | |||||
Knowledge transfer: | |||||
|
| ||||
Resource Planning: |
0 Comments