What is the purpose of planning?
Identify goal(s) and what needs to be done and ID specific stories against the goal(s)
Planning tickets to bring into Ready for Dev to work on (most of which to complete) in next iteration.
Ditto above, plus check the capacity of the team in the next two weeks (availability etc)
Resolve prioritisation / sequencing
Assessing work in progress on the board against refreshed goals
Planning is not a refinement session - this is what the Refinement session 2 days before is about
Goal(s) for the next Iteration:
Statement:
Focusing on
Team - Revalidation connections
Continue with the private beta and proactively seek user feedback from all Leads and team (who may have own ideas and insights) - will we get the two outstanding tickets completed? Review where we are and work out next step.
Team availability (e.g., Leave & Events):
Non-Kanban work (this iteration):
Arrange a call with Revalidation leads ( Connections) to ascertain MVP
TBD: - TIS21-4876Getting issue details... STATUS HLE session held. Rob has an upcoming call with Stephen Loughran to get an email list if possible. (outcome to help support with GMC’s email query)]
Work lined up for the iteration | ||
---|---|---|
0 | Live Defect | From last iteration: |
Support | Carried over… Review sync issues in Revalidation - next step = High Level Estimation Waiting | |
1 | Revalidation - Connections | From last iteration: Private Beta in flight Private Beta waiting |
2 | Other Tech improvement | |
3 | Post funding | Waiting
To be refined Can we look at getting a delivery plan set up so this work can be prioritised and sequenced alongside rolling user feedback. Epic = - TIS21-3273Getting issue details... STATUS - we queried the scope around delivery plan. Further conversation to fletch some things. Based on discussion around what our actual focus is. |
4 | Programme Membership | In flight |
5 | TIS assessment | |
6 | ESR | If there is capacity/willingness to refine: - TIS21-4985Getting issue details... STATUS |
17 | Data work | From last iteration: - TIS21-4838Getting issue details... STATUS |
11 | Retro actions |
|
LTFT discovery | Cross-team effort, involving Ade B and Ade A . Ade Babalola: LTFT Discovery Plan.xlsx
| |
12 | Roadmap review | TIS Admin product roadmap.pptx Explode-out revalidation to produce a Revalidation Roadmap (does the team want to start to explore this)? |
Goal(s) for the next Iteration:
Statement:
Focusing on
Team - Revalidation connections
Continue with the private beta and proactively seek user feedback from all Leads and team (who may have own ideas and insights) - will we get the two outstanding tickets completed? Review where we are and work out next step.
Team availability (e.g., Leave & Events):
Pepe (A/L) 13th-15th Sept
Yafang (A/L) 15th-22nd of Sept
Cai (A/L) 18th-22nd of Sept
Non-Kanban work (this iteration):
Arrange a call with Revalidation leads ( Connections) to ascertain MVP IF WE FEEL that the F1 ticket and sync work will be advanced in this Iteration.
TBD: - TIS21-4876Getting issue details... STATUS HLE session held.
Work lined up for the iteration | ||
---|---|---|
0 | Live Defect | From last iteration: Linked to - https://hee-tis.atlassian.net/l/cp/KC01PH24 - TIS21-4689Getting issue details... STATUS Linked to - https://hee-tis.atlassian.net/l/cp/4kLjYF8T status? - TIS21-4864Getting issue details... STATUS -(AdHoc) |
1 | Connections MVP dependent | In for development Review sync issues in Revalidation
-
TIS21-4956Getting issue details...
STATUS
High priority as part of the MVP- with time box for 2 days. To further liaise with Pepe when back. |
2 | Revalidation - Connections | Private Beta in flight - TIS21-4154Getting issue details... STATUS Dev plan to finish this ticket in the next one /two days ready to be presented at Review. - TIS21-4690Getting issue details... STATUS Private Beta feedback Need to extend the access to the Private Beta, so looking to Ade B to continue a dialogue and to understand likely posy MVP developments and issues. |
3 | Revalidation designated body merger | I (Rob) needs to develop a ticket for this work. Tow London designated bodies are to become one. Depending on the size of this work (refinement) will determine when it is to be done, so starting this off will be something ASAP. |
4 | Other Tech improvement | In flight - does this involve us? In for development - does these involve us? Is it a Pepe one? |
5 | Changes to email | Specifically I would like to understand how to update all staff emails to NHS.NET (1) on Keycloak and (2) the Reval users who are different? It would be very helpful to get this understood so we can make sure resources are in place to support the change. We now have a spreadsheet from IT with “old” and “new” so we can map the chnges. |
6 | Post funding | - TIS21-95Getting issue details... STATUS Next - TIS21-4875Getting issue details... STATUS Would like to progress refining these tickets as they will be the next in line post MVP. |
7 | Programme Membership | In flight
-
TIS21-3785Getting issue details...
STATUS
|
8 | BUGS | - TIS21-4958Getting issue details... STATUS Potential ticket to come in to the iteration- impact audit of GMC end of October/November so would be important to get this work submitted. |
9 | ESR | In flight |
10 | Data work | In flight - TIS21-4838Getting issue details... STATUS - TIS21-5019Getting issue details... STATUS - TIS21-4620Getting issue details... STATUS -AdHoc Huddle
|
11 | Retro actions | |
12 | LTFT discovery |
|
13 | Roadmap review | TIS Admin product roadmap.pptx Explode-out revalidation to produce a Revalidation Roadmap (does the team want to start to explore this)? |
Goal(s) for the next Iteration:
Statement:
Focusing on
Team - Revalidation connections
Continue with the private beta and proactively seek user feedback from all Leads and team (who may have own ideas and insights) - will we get the two outstanding tickets completed? Review where we are and work out next step.
Team availability (e.g., Leave & Events):
Pepe (A/L) 31st of Aug- 15th of September
Yafang (A/L) 1st September
Non-Kanban work (this iteration):
Arrange a call with Revalidation leads ( Connections) to ascertain MVP
TBD: - TIS21-4876Getting issue details... STATUS HLE session held. Rob has an upcoming call with Stephen Loughran to get an email list if possible. (outcome to help support with GMC’s email query)
Work lined up for the iteration | ||
---|---|---|
0 | Live Defect | From last iteration: Linked to - https://hee-tis.atlassian.net/l/cp/KC01PH24 - TIS21-4689Getting issue details... STATUS Linked to - https://hee-tis.atlassian.net/l/cp/4kLjYF8T status? - TIS21-4864Getting issue details... STATUS -(AdHoc) |
Support | Carried over… Review sync issues in Revalidation - next step = High Level Estimation - TIS21-4956Getting issue details... STATUS Waiting | |
1 | Revalidation - Connections | From last iteration: Private Beta in flight - TIS21-4154Getting issue details... STATUS Private Beta waiting - TIS21-4690Getting issue details... STATUS Private Beta feedback ?Potential Bug ticket to be raised but further looking at is required.- Cai to email GMC Data Apart from the above two tickets, is there anything else outstanding? What about the observation that the system is slow?- Investigation ticket to be raised if we don’t already have one( To be created after this planning session). AdHoc refinement. |
2 | Other Tech improvement | Liaise with Andy Dingley re: https://hee-tis.atlassian.net/browse/TIS21-1209 |
3 | Post funding | Waiting - TIS21-95Getting issue details... STATUS To be refined - TIS21-4875Getting issue details... STATUS Can we look at getting a delivery plan set up so this work can be prioritised and sequenced alongside rolling user feedback. Epic = - TIS21-3273Getting issue details... STATUS - we queried the scope around delivery plan. Further conversation to fletch some things. Based on discussion around what our actual focus is. |
4 | Programme Membership | In flight |
5 | TIS assessment | |
6 | ESR | - TIS21-213Getting issue details... STATUS (Tech Improvement) If there is capacity/willingness to refine: - TIS21-4985Getting issue details... STATUS |
17 | Data work | From last iteration: - TIS21-4838Getting issue details... STATUS |
11 | Retro actions | |
LTFT discovery | Watching brief. Cross-team effort, involving Ade B in the first instance. What stage are we in now? research stage(ongoing) -Sending out invites for interviews - TIS21-4417Getting issue details... STATUS Ade Babalola: LTFT Discovery Plan.xlsx
| |
12 | Roadmap review | TIS Admin product roadmap.pptx Explode-out revalidation to produce a Revalidation Roadmap (does the team want to start to explore this)? |
Goal(s) for the next Iteration:
Statement:
Focusing on
Team - Revalidation connections
Continue with the private beta and proactively seek user feedback from all Leads and team (who may have own ideas and insights) - will we get the two outstanding tickets completed? Review where we are and work out next step.
Team availability (e.g., Leave & Events):
Steve (A/L) 16th to 18th of August
Jay (A/L) 24th and 25th of August
Cai (A/L) 21st of August
Bank Holiday: 28th of August
Non-Kanban work (this iteration):
Arrange a call with Revalidation leads ( Connections) to ascertain MVP
Work lined up for the iteration | ||
---|---|---|
0 | Live Defect | From last iteration: Linked to - https://hee-tis.atlassian.net/l/cp/KC01PH24 - TIS21-4687Getting issue details... STATUS (AdHoc) - TIS21-4689Getting issue details... STATUS Linked to - https://hee-tis.atlassian.net/l/cp/4kLjYF8T status? - TIS21-4864Getting issue details... STATUS -(AdHoc) |
Support | Carried over… Review sync issues in Revalidation - next step = High Level Estimation - TIS21-4956Getting issue details... STATUS Waiting | |
1 | Revalidation - Connections | From last iteration: Private Beta in flight - TIS21-4154Getting issue details... STATUS Private Beta waiting - TIS21-4690Getting issue details... STATUS Private Beta feedback Apart from the above two tickets, is there anything else outstanding? What about the observation that the system is slow?- |
2 | Other Tech improvement | - TIS21-4954Getting issue details... STATUS (preventative) AdHoc Continuing: |
3 | Post funding | Waiting - TIS21-95Getting issue details... STATUS To be refined - TIS21-4875Getting issue details... STATUS Can we look at getting a delivery plan set up so this work can be prioritised and sequenced alongside rolling user feedback. Epic = - TIS21-3273Getting issue details... STATUS - we queried the scope around delivery plan. Further conversation to fletch some things. |
4 | Programme Membership | In flight - TIS21-3785Getting issue details... STATUS TIS Assessment |
5 | Email Change |
-
TIS21-4876Getting issue details...
STATUS
Can we have a session please to work out what next? Rob has an upcoming call with Stephen Loughran to get an email list if possible. |
6 | ESR | - TIS21-213Getting issue details... STATUS (Tech Improvement) - TIS21-4775Getting issue details... STATUS Blocked! There’s a blocker with built server - Raising ?a ticket??? cross-team???Not clear on the blocker-outside this planning. |
17 | Data work | From last iteration: |
11 | Retro actions | |
LTFT discovery | Watching brief. Cross-team effort, involving Ade B in the first instance. | |
12 | Roadmap review | TIS Admin product roadmap.pptx Explode-out revalidation to produce a Revalidation Roadmap (does the team want to start to explore this)? |
Goal(s) for the next Iteration:
Statement:
Focusing on
Team - Revalidation connections
Continue with the private beta and proactively seek user feedback from all Leads and team (who may have own ideas and insights) - will we get the two outstanding tickets completed?
Team availability (e.g., Leave & Events):
Pepe ~1-2 days TBA
James (A/L) 4th-11th
Steve (A/L) 7th-18th
Team catch up in LONDON 10.08.23
Rob AL 3/4 August
Non-Kanban work (this iteration):
Work lined up for the iteration | ||
---|---|---|
0 | Live Defect | Linked to - https://hee-tis.atlassian.net/l/cp/KC01PH24 - TIS21-4687Getting issue details... STATUS - TIS21-4689Getting issue details... STATUS
|
Support | Helpful to understand and get a position on the perception that Recommendations is unstable. Suggestions on how to move this forward? Rob to raise a ticket? Spike, High level estimation to discuss around it. | |
1 | Revalidation - Connections | From last iteration: Private Beta in flight - TIS21-4154Getting issue details... STATUS Huddle to help progress this ticket ? Today Private Beta waiting - TIS21-4690Getting issue details... STATUS Private Beta feedback Feedback from Teams → Connections Private Beta - TIS21 Confluence Space - Confluence (atlassian.net) >> Can we just give this a quick review, including updating recent feedback if applicable. Question >>> Are the above two tickets what has been ID’ed for the Private Beta? |
2 | Connections user research | Carried over from last Planning → Do we need to tidy up the revalidation material on Confluence? ?Team discussion and suggestion re: Reval materials on confluence? Rob started informally logging this and will share when advanced if that’s of interest? |
3 | Other Tech improvement | New: - TIS21-4862Getting issue details... STATUS (Cross-team) Continuing: |
Post funding | From last iteration: In flight - TIS21-4802Getting issue details... STATUS Waiting - TIS21-95Getting issue details... STATUS To be refined - TIS21-4875Getting issue details... STATUS ADHOC refinement ?today/tomorrow Can we look at getting a delivery plan set up so this work can be prioritised and sequenced alongside rolling user feedback. Epic = - TIS21-3273Getting issue details... STATUS | |
4 | Programme Membership | Waiting - TIS21-3785Getting issue details... STATUS are we intending to bring this in? It is refined and of medium effort. ? → There’s an improvement that Joseph (Pepe) Kelly looked into about changing the way Conditions Of Joining (acceptance) are mapped - - TIS21-4759Getting issue details... STATUS 3 Amigo in this iteration. Not intending to do this work in this Iteration but it will be good to have it refined. |
| Email Change | Contended for High Level Estimation and to add related stories so these can be prioritised and developed for future work --- - TIS21-4876Getting issue details... STATUS Friday HLE to scope out this work. P1 |
6 | ESR | - TIS21-213Getting issue details... STATUS (Tech Improvement) |
17 | Data work | From last iteration: - TIS21-4838Getting issue details... STATUS - TIS21-4612Getting issue details... STATUS - TIS21-4688Getting issue details... STATUS - TIS21-4620Getting issue details... STATUS - To be 3 Amigo’d on the completion of the 4838 |
11 | Retro actions | From last iteration: - TIS21-4781Getting issue details... STATUS |
LTFT discovery | cross-team effort, involving Ade B in the first instance. ? Need for team update regarding this work. | |
12 | Roadmap review | TIS Admin product roadmap.pptx Explode-out revalidation to produce a Revalidation Roadmap (does the team want to start to explore this)? |
Goal(s) for the next Iteration:
Statement:
Focusing on
Team - Revalidation connections
Continue with the private beta and proactively seek user feedback from all Leads and team (who may have own ideas and insights).
Team availability (e.g., Leave & Events):
Pepe on A/L 19.7.23 @14:00 to 21.7.23
Jay on A/L 20/7-21/7
Cai, Stan on 24/7
Steve 20/7
Non-Kanban work (this iteration):
Work lined up for the iteration | ||
---|---|---|
0 | Live Defect | - TIS21-4687Getting issue details... STATUS - TIS21-4689Getting issue details... STATUS Live Defect: 19.7.23 ticket to be created. |
1 | Revalidation - Connections | In flight
MVP improvements ready - TIS21-4690Getting issue details... STATUS MVP improvements from feedback Feedback from Teams → Connections Private Beta - TIS21 Confluence Space - Confluence (atlassian.net) Assume 4548 makes this ticket unnecessary for the time being? #8 > Bring in - TIS21-4154Getting issue details... STATUS Now that the spike has been completed can this ticket be revise, refined and put in. |
2 | Connections user research | Proactively seek additional feedback. from users on the UR channel, UR to continue to ensure users are engaging with regular updates on Teams. Carried over from last Planning → Do we need to tidy up the revalidation material on Confluence? ?Team discussion and suggestion re: Reval materials on confluence? Rob started informally logging this and will share when advanced if that’s of interest? |
3 | Other Tech improvement | |
Post funding | - TIS21-4802Getting issue details... STATUS - TIS21-95Getting issue details... STATUS get refined and lined-up (ADHoc? Today or tomorrow) - TIS21-4805Getting issue details... STATUS for investigation Can we create a UR channel and add the Leads and other participants so we can get QA as appropriate? Rob happy to set this up to follow previous precedent. Lunch and learn to be arranged: Catherine to put in team’s calendar | |
4 | Programme Membership | - TIS21-3785Getting issue details... STATUS are we intending to bring this in? It is refined and of medium effort. There’s an improvement that Joseph (Pepe) Kelly looked into about changing the way Conditions Of Joining (acceptance) are mapped - was this done? - TIS21-4759Getting issue details... STATUS 3 Amigo in this iteration. |
| Email Change | ? Spike for an investigation: How do we update TIS admin and revalidation email to the current NHS.NET email: Get a call with the team: Catherine to arrange. |
6 | ESR | Prevent irreparable loss of the ESR interface due to MongoDB Atlas contract not being in place from 1st Aug. Rob supporting with this query
-
TIS21-213Getting issue details...
STATUS
(Tech Improvement) conversation on how we achieve the goal of this ticket- |
17 | Data work | |
11 | Retro actions | |
12 | Roadmap review | TIS Admin product roadmap.pptx Explode-out revalidation to produce a Revalidation Roadmap (does the team want to start to explore this)? |
Goal(s) for the next Iteration:
Statement:
Focusing on
Team - Revalidation connections
Continue with the private beta and proactively seek user feedback from all Leads and team (who may have own ideas and insights).
Develop a delivery plan for the final push to get Connections in a state for adoption - current changes based on the UR. What stories do we have?
Demonstrate the MVP is being refined and improved.
Team availability (e.g., Leave & Events):
Stan (A/L) 5th - 7th of July
Pepe (A/L) 6th July + probably 11th/12th July
Non-Kanban work (this iteration):
Pen Test planning in light of Connections release? Not required.
Rob / Catherine to check up on preferences for London DB merger and support for bulk upload re connections with GMC.
Work lined up for the iteration |
---|
Work lined up for the iteration |
---|
Work lined up for the iteration | ||
---|---|---|
0 | Live Defect | |
1 | Revalidation - Connections | In flight - TIS21-4548Getting issue details... STATUS MVP improvements ready - TIS21-4574Getting issue details... STATUS
MVP improvements from feedback Feedback from Teams → Connections Private Beta - TIS21 Confluence Space - Confluence (atlassian.net) #13 > - TIS21-4662Getting issue details... STATUS (this is a fault/bug)(P1) #6 > Send to GMC comes up as “Save”, but should be “Submit” so it’s clear what's happening? Create new ticket and to be 3 Amigo with Steve ?today #7 > Bring in - TIS21-4526Getting issue details... STATUS – To create a new ticket for a specific filter which is addressing programme owner(P2) #9 > Dummy record removal - TIS21-4690Getting issue details... STATUS #8 > Bring in
-
TIS21-4154Getting issue details...
STATUS
Creating of Spike ticket MVP outstanding --- these have gone back to the backlog. Are they necessary for MVP? - TIS21-4040Getting issue details... STATUS - TIS21-4039Getting issue details... STATUS Aim to get two above tickets refined this Iteration? *** can we go through the five Epics and ID any tickets not done and work out whether the still have legs? Mini backlog refinement of MVP related. Catherine and Rob to take time and go through this. |
2 | Connections user research | Proactively seek additional feedback. from users on the UR channel, UR to continue to ensure users are engaging with regular updates and emails Do we need to tidy up the revalidation material on Confluence? ?Team discussion and suggestion re: Reval materials on confluence |
3 | Other Tech improvement | Generate stories from MongoDB: Joseph (Pepe) Kelly to create tickets out of this.
|
4 | Programme Membership | - TIS21-2403Getting issue details... STATUS - TIS21-3785Getting issue details... STATUS There’s an improvement that Joseph (Pepe) Kelly looked into about changing the way Conditions Of Joining (acceptance) are mapped |
| Bulk uploads | |
5 | Post funding UR | Can we get some priority tickets developed so they can be lined up, please? Catherine, James, Ade B and Ade A, Rob etc. Arrange an hour conversation to work out priority tickets. |
6 | ESR | - TIS21-213Getting issue details... STATUS (Tech Improvement) conversation on how we achieve the goal of this ticket- we have a blocker: internal blocker - ensure token has the necessary access |
17 | Data work | - TIS21-4612Getting issue details... STATUS |
11 | Retro actions | - TIS21-4751Getting issue details... STATUS Plus to be added from yesterday’s session. |
12 | Roadmap review | TIS Admin product roadmap.pptx Explode-out revalidation to produce a Revalidation Roadmap (does the team want to start to explore this)? |
Goal(s) for the next Iteration:
Statement:
Focusing on
Team - Revalidation connections
Continue with the private beta and proactively seek user feedback from all Leads and team (who may have own ideas and insights).
Socialise user feedback insights to team so that we can make judgements on improvements - which may need to be validated with users.
Identified MVP improvements prioritised on the fly.
Demonstrate the MVP is being refined and improved.
Team availability (e.g., Leave & Events):
Cai (A/L) 26th- 30th of June
Steve (A/L) 23rd of June
Pepe (A/L) 26th -29th of June (TBC)
James H (A/L)29th-3rd of July
Rob (A/L) prob 26-27 June (TBC)
Non-Kanban work (this iteration):
ESR meeting TBA (Rob leading on this)
GMC meeting - cover-off London DB merger, the stage update and support for bulk connections.
Pen Test planning in light of Connections release?
Work lined up for the iteration |
---|
Work lined up for the iteration | ||
---|---|---|
0 | Live Defect | |
1 | Revalidation - Connections | In flight - TIS21-4548Getting issue details... STATUS Cai and Yafang meeting after planning. MVP improvements ready - TIS21-4574Getting issue details... STATUS MVP outstanding (when are these necessary to be done)? - TIS21-4040Getting issue details... STATUS - TIS21-4039Getting issue details... STATUS MVP improvements from feedback Feedback from Teams → Connections Private Beta - TIS21 Confluence Space - Confluence (atlassian.net) #6 > Send to GMC comes up as “Save”, but should be “Submit” so it’s clear what's happening? #9 > Dummy record removal - TIS21-4690Getting issue details... STATUS #7 > Bring in - TIS21-4526Getting issue details... STATUS – ? Is this dependent on further insights? #8 > Bring in - TIS21-4154Getting issue details... STATUS Would need to be refined. #13 > - TIS21-4662Getting issue details... STATUS (ADHOC refinement as a matter of urgency?) |
2 | Connections user research | Get outputs from the UR sessions analysed and socialised so we can confirm suggested improvements and join up with Teams feedback. User journey outputs? Dependency on insights then to plan team feedback session. |
3 | Tech improvement | Generate stories from MongoDB: Joseph (Pepe) Kelly suggesting to create tickets out of this? And this aim to come in in this Iteration?
Book second day |
4 | Programme Membership | - TIS21-2403Getting issue details... STATUS - TIS21-2399Getting issue details... STATUS (should be mostly Reviews) |
Bulk uploads | James would like us to consider these… They are dependent on 2403 (I think). Opinions? - TIS21-4651Getting issue details... STATUS → is this a bug? - TIS21-4508Getting issue details... STATUS Are we in a position to bring these in? At least to get them refined so they can be lined up. | |
5 | Post funding UR | Can we get some priority tickets developed so they can be lined up, please? |
6 | ESR | - TIS21-213Getting issue details... STATUS (Tech Improvement) conversation on how we achieve the goal of this ticket- we have a blocker: internal blocker - ensure token has the necessary access KSS ESR issue(s) to be investigated. |
17 | Data work | - TIS21-4612Getting issue details... STATUS Dependency on 4688 |
11 | Retro actions | |
12 | Roadmap review | TIS Admin product roadmap.pptx Explode-out revalidation to produce a Revalidation Roadmap (does the team want to start to explore this)? |
Goal(s) for the next Iteration:
Statement:
Focusing on
Team - Revalidation connections - Go live with three teams ( Wessex, Nwest, London &KSS)as part and cycle round the UR so we can judge immediate improvements.
Team availability (e.g., Leave & Events):
James Harris (A/L) 6th to the 9th of June
Pepe (A/L): Wed 7th (Today) pm
Jay (A/L) half day on Friday 9th June
? Rob (A/L) next week (TBC)
Non-Kanban work (this iteration):
ESR meeting TBA (Rob leading on this)
Work lined up for the iteration |
---|
Work lined up for the iteration |
---|
Work lined up for the iteration | ||
---|---|---|
0 | Live Defect |
|
1 | Revalidation - Connections | This Iteration: - TIS21-4548Getting issue details... STATUS Bring in - TIS21-4526Getting issue details... STATUS – this needs to be refined. It will address a shortfall in usability of the Discrepancy list by having a default filtering by DB. It will also introduce filtering from which we can iterate based on feedback. Need to review the user research and cycle round any improvements ASAP. These may occur in these two weeks. >>> Carry on with logic tickets. Do we need to review and clear tickets no longer required etc. (3 Amigos) on the logic tickets this iteration. >>> Get three teams on production, which should happen today. |
2 | Connections user research | We need an epic created for this work, so that we can capture and ticket-up things that we agree need to be done either as part of immediate improvement, or for later prioritisation. Capturing UR work / integrating it into JIRA. Ade B: |
Stage environment | Is there anything we need to do on Stage to synchronise with the GMC update of their Test system? Would need planning and refinement re: GMC update of stage environment. | |
TIS | Monitoring and Logging ticket - add Sentry to TCS (& Reference). - TIS21-4560Getting issue details... STATUS | |
3 | Tech improvement | MongoDB: Updating docs & planning with external expertise to do a subset of:
|
4 | Programme Membership | - TIS21-2403Getting issue details... STATUS - TIS21-2399Getting issue details... STATUS (should be mostly Reviews) |
Bulk uploads | James would like us to consider these… They are dependent on 2403 (I think). Opinions? | |
5 | Post funding UR | When James is back it would be very helpful to start to develop and refine the related user stories, with their priority. |
6 | ESR | - TIS21-213Getting issue details... STATUS (Tech Improvement) conversation on how we achieve the goal of this ticket- no current blocker |
17 | Data work | - TIS21-4567Getting issue details... STATUS - TIS21-4457Getting issue details... STATUS |
11 | Retro actions | - TIS21-4625Getting issue details... STATUS Links in with (2)Connections user research |
12 | Roadmap review | TIS Admin product roadmap.pptx Explode-out revalidation to produce a Revalidation Roadmap (does the team want to start to explore this)? |
Goal(s) for the next Iteration:
Statement:
Focusing on
Team - Revalidation connections - getting towards Live + starting UR
Team availability (e.g., Leave & Events):
Ade A (A/L) 25/5/23
James Harris (A/L) 6/6/23
Rob (A/L) Fri 26 and Tues 30th
Bank Holiday: 29th of May 2023
Non-Kanban work (this iteration):
Discussions: Reval Leads-connection update
Speaking with Wales about what TIS does. Wales are considering alternatives to Intrepid (which was used by HEE & NI before moving to TIS)- Planning to meet again 1st of June
Work lined up for the iteration |
---|
Work lined up for the iteration | ||
---|---|---|
0 | Live Defect | |
1 | Revalidation - Connections | This Iteration: - TIS21-4555Getting issue details... STATUS - TIS21-4554Getting issue details... STATUS - TIS21-4548Getting issue details... STATUS >>> Carry on with logic tickets. Do we need to review and clear tickets no longer required etc. (3 Amigos) on the logic tickets this iteration. >>> Have we picked up any other immediate priorities that we need to resolve this iteration?- Clarifying on discrepancies list(for further discussion) >>> Need to get all Leads on Stage >>> Prep for one/two teams as early adopters. |
2 | Connections user research | Can we create an Epic to frame this work? Covers user research and the any improvements that come out of this? This will help with vis |
3 | Tech improvement | |
4 | Programme Membership | - TIS21-2403Getting issue details... STATUS - TIS21-2399Getting issue details... STATUS (should be mostly Reviews) |
5 | Post funding UR | Session with team on Post Funding (retro action) Going through needs based on categorisation Work to start to develop user stories within the Epic. Ade B, James, Catherine and Rob etc( to be considered for next iteration) |
6 | ESR | - TIS21-213Getting issue details... STATUS (Tech Improvement) conversation on how we achieve the goal of this ticket- no current blocker |
17 | Data work | |
11 | Retro actions | - TIS21-4453Getting issue details... STATUS ? to be discussed with team then( To link this with Stan’s planned work around our Jira dashboard) - TIS21-4570Getting issue details... STATUS : Ade B to guide on this on post funding. |
12 | Roadmap review | TIS Admin product roadmap.pptx Explode-out revalidation to produce a Revalidation Roadmap (does the team want to start to explore this)? |
.
Goal(s) for the next Iteration:
Statement:
Focusing on
Team - Revalidation connections - What value can we deliver?
UR - Post funding Research Plan and user needs to start.
Team availability (e.g., Leave & Events):
Yafang15th -19th of May
Bank Holiday: 29th of May 2023
Non-Kanban work (this iteration):
Review survey results. Can we get a call in with Team?
Discussions: Need to get a call in with the team to move work on user management with Ade B and Catherine_ to confirm a date?
Speaking with Wales about what TIS does. Wales are considering alternatives to Intrepid (which was used by HEE & NI before moving to TIS)-
Work lined up for the iteration |
---|
Work lined up for the iteration | ||
---|---|---|
0 | Live Defect | |
1 | Revalidation - Connections | This Iteration: - TIS21-3734Getting issue details... STATUS - TIS21-4157Getting issue details... STATUS - TIS21-4510Getting issue details... STATUS - TIS21-4510Getting issue details... STATUS - TIS21-4526Getting issue details... STATUS -Epic? Is this post MVP improvement work led by the UR and prob FE too.
|
3 | TIS (Infrastructure) | |
4 | Programme Membership | Refinement Cross-Team for tickets in backlog TIS21-2399 & TIS21-2403. liaising with Trainee team re-moving this tickets forward Clause: currently not refined- Cross team refinement For Yafang and Pepe + trainee team COJ- trainee team are currently working along side tickets in questioned ? Trainee team need to unblock work to prioritise in order to allow Admin to move work on- Encourage trainee team to bring ? tickets into their own iteration~ |
7 | Technical improvement | |
9 | Post funding UR | User mapping has been done and will be shared with the Team. Joint working with Data analyst to review feedback of our users Research plan also to do: to be completed upon Alpha phase Focus work on this iteration : Post funding, reviewing phase of user feed back |
10 | Retro actions | |
11 | Roadmap review | Can we just sense check? TIS Admin product roadmap.pptx Explode-out revalidation to produce a Revalidation Roadmap |
Goal(s) for the next Iteration:
Statement:
Focusing on
Team - Revalidation connections - What value can we deliver?
UR - Post funding Research Plan and user needs to start.
Team availability (e.g., Leave & Events):
Stan (A/L) 25-28th April
? Rob (A/L) 5th May
Bank Holiday: 1st of May and 8th of May
Non-Kanban work (this iteration):
Review survey results. Can we get a call in with Team?
Discussions: Need to get a call in with the team to move work on user management 27/4/23 with Ade B and Catherine
Work lined up for the iteration |
---|
Work lined up for the iteration | ||
---|---|---|
0 | Live Defect | |
1 | Revalidation - Connections | This Iteration: - TIS21-3961Getting issue details... STATUS - TIS21-3962Getting issue details... STATUS - TIS21-3963Getting issue details... STATUS - TIS21-4038Getting issue details... STATUS - TIS21-3772Getting issue details... STATUS
|
3 | TIS (Infrastructure) | - TIS21-4354Getting issue details... STATUS Ongoing work with Pepe |
4 | Programme Membership | Refinement Cross-Team for tickets in backlog TIS21-2399 & TIS21-2403. liaising with Trainee team re-moving this tickets forward Clause: currently not refined- Cross team refinement For Yafang and Pepe + trainee team
|
7 | Technical improvement | High-Level plan & refinement for ESR on ECS work… (Jayanta Saha) - TIS21-213Getting issue details... STATUS There is some additional Tech Improvement that doesn’t directly involve services for the Connections MVP similar to - TIS21-3874Getting issue details... STATUS Tech team sharing |
9 | Post funding UR | User mapping has been done and will be shared with the Team. Research plan also to do. Focus work on this iteration : Post funding, gathering user feedback~ |
10 | Retro actions |
|
11 | Roadmap review | Can we just sense check? TIS Admin product roadmap.pptx Explode-out revalidation to produce a Revalidation Roadmap |
Goal(s) for the next Iteration:
Statement:
Focusing on
Team - Revalidation connections - What value can we deliver?
UR - Post funding Research Plan and user needs to start.
Team availability (e.g., Leave & Events):
Stan(Paternity) 12-18th April
Stan (A/L) 19th-25th April
Cai (A/L) 12th- 14th of April
Steve (A/L) 13th-14th of April
Bank Holiday:
Non-Kanban work (this iteration):
Review survey results. Can we get a call in with Team?
Discussions: Need to get a call in with the team to move work on user management
Work lined up for the iteration | ||
---|---|---|
0 | Live Defect | - TIS21-4367Getting issue details... STATUS … Just RCA & Actions left? |
1 | Revalidation - Connections | This Iteration: - TIS21-3961Getting issue details... STATUS - TIS21-3962Getting issue details... STATUS - TIS21-3963Getting issue details... STATUS - TIS21-3874Getting issue details... STATUS Last Iteration: - TIS21-3774Getting issue details... STATUS - next work in line (for refinement) Team meeting to go through Logic tickets and ? re-prioritise as needed and we should put additional tickets into the Ready for Development pile so they can be taken in as required. Currently there is only one ticket |
3 | TIS (Infrastructure) | - TIS21-4354Getting issue details... STATUS Ongoing work with Pepe and the team |
4 | Programme Membership | Refinement Cross-Team for tickets in backlog TIS21-2399 &TIS21-2403. liaising with Trainee team re-moving this tickets forward Clause: currently not refined- For Admin team to liaise with trainee team re: tickets |
7 | Technical improvement | High-Level plan & refinement for ESR on ECS work… (Jayanta Saha) - TIS21-213Getting issue details... STATUS - TIS21-3874Getting issue details... STATUS Not refined but need to do (sorry from Joseph (Pepe) Kelly ): - TIS21-4370Getting issue details... STATUS |
9 | Post funding UR | User mapping has been done and will be shared with the Team. Research plan also to do. Start the research: Ongoing work |
10 | Retro actions | - TIS21-4368Getting issue details... STATUS - TIS21-4369Getting issue details... STATUS - TIS21-4319Getting issue details... STATUS this work to be linked with Stan’s Jira Dashboard
|
11 | Roadmap review | Can we just sense check? TIS Admin product roadmap.pptx Explode-out revalidation to produce a Revalidation Roadmap |
Goal(s) for the next Iteration:
Statement:
Focussing on
Developers - Designated Body changes - Can we be clear what we doing before 27th to test and investigate and what we are doing after 27th to implement. This may include a tail for further work after the codes have been changed.
Developers - Revalidation connections - What value can we deliver?
Team - To produce a delivery plan for the Connections work.
UR - Resolve what the Revalidation Alpha reporting objectives are?
UR - Post funding Research Plan and user needs to start.
Team availability (e.g., Leave & Events):
Stan(Paternity) 3rd-18th April
Jay (A/L) 13th –31st March
Pepe 4th April TBC
Ade A (A/L) 27th – 31st March
Rob 30th and 31st of March
Easter holiday- 7th and 10th April
Non-Kanban work (this iteration):
Review survey results. Can we get a call in with Team?
Work lined up for the iteration |
---|
Work lined up for the iteration | ||
---|---|---|
1 | Revalidation - Connections | - TIS21-3774Getting issue details... STATUS - next work in line (for refinement) - TIS21-3874Getting issue details... STATUS Devs Team meeting to go through Logic tickets and ? re-prioritise as needed |
2 | Merger | |
2 | Revalidation Connections - Overview | Summary of work done and work to do - formation of a delivery plan |
3 | Certification | |
4 | Programme Membership | Refinement Cross-Team for tickets in backlog TIS21-2399 &TIS21-2403. ? |
5 | Bulk Upload | |
6 | Data work | |
7 | Technical improvement | |
8 | Revalidation reporting research / discovery | In progress → UR - Resolve Alpha approach |
9 | Post funding UR | Research plan and user mapping Start the research: Ongoing work |
10 | Retro actions | - TIS21-4318Getting issue details... STATUS - TIS21-4319Getting issue details... STATUS
|
11 | Roadmap review | Can we just sense check? TIS Admin product roadmap.pptx Explode-out revalidation to produce a Revalidation Roadmap |
Goal(s) for the next Iteration:
Statement:
Focussing on
Developers - Designated Body changes - Can we be clear what we doing before 27th to test and investigate and what we are doing after 27th to implement. This may include a tail for further work after the codes have been changed.
Developers - Revalidation connections - What value can we deliver?
Team - To produce a delivery plan for the Connections work.
UR - Resolve what the Revalidation Alpha reporting objectives are?
UR - Post funding Research Plan and user needs to start.
Team availability (e.g., Leave & Events):
Ade A (A/L) 13th -17th March
Stan(A/L) 13th -17th March
Jay (A/L) 13th –31st March
Yafang (A/L) 20th – 24th March
Pepe 22nd-28th March
Ade A (A/L) 27th – 31st March
Non-Kanban work (this iteration):
Review survey results. Can we get a call in with Team?
Work lined up for the iteration |
---|
Work lined up for the iteration | ||
---|---|---|
1 | Revalidation - Connections | - TIS21-3774Getting issue details... STATUS - next work in line (for refinement) |
2 | Merger | - TIS21-4290Getting issue details... STATUS |
2 | Revalidation Connections - Overview | Summary of work done and work to do - formation of a delivery plan |
3 | ESR | Ready → File management → - TIS21-146Getting issue details... STATUS |
4 | Programme Membership | Refinement Cross-Team for tickets in backlog TIS21-2399 &TIS21-2403. ? |
5 | Bulk Upload | |
6 | Data work | |
7 | Technical improvement | |
8 | Revalidation reporting research / discovery | In progress → UR - - TIS21-4013Getting issue details... STATUS Resolve Alpha approach |
9 | Post funding UR | Research plan and user mapping Start the research |
10 | Retro actions | - TIS21-4318Getting issue details... STATUS - TIS21-4319Getting issue details... STATUS
- TIS21-4217Getting issue details... STATUS |
11 | Roadmap review | Can we just sense check? TIS Admin product roadmap.pptx Explode-out revalidation to produce a Revalidation Roadmap |
Goal(s) for the next Iteration:
Statement: Revalidation Connections MVP
Focussing on
Designated Body changes - Can we be clear what we doing before 27th to test and investigate and what we are doing after 27th to implement. This may include a tail for further work after the codes have been changed.
Revalidation connections - What value can we deliver?
To produce a delivery plan for the Connections work. This may determine whether we stop supporting Revalidation V1 on 27th March.
Post funding Research Plan and user needs to start. Is this an epic to be created?
Team availability (e.g., Leave & Events):
User Research Sessions - a number of the team
James H (A/L) 27 Feb- 3rd March
Cai(A/L) 6th -10th of March
Ade A (A/L) 13th -17th March
Stan(A/L) 13th -17th March
Jay (A/L) 13th –31st March
Jay 10th March
Cai 3rd March
Non-Kanban work (this iteration):
Collate ESR work, specifically list of issues. Planning to get a call in. Rob/?Pepe Should happen in the next two weeks, but keeps being bumped. Would like to review Stan’s work as that may help frame the first meeting with ESR Leads.
Review survey results. Can we get a call in with Team.
Work lined up for the iteration |
---|
Work lined up for the iteration | ||
---|---|---|
1 | Revalidation - Connections | - TIS21-3774Getting issue details... STATUS - next work in line (for refinement) - TIS21-3874Getting issue details... STATUS Look at - TIS21-4041Getting issue details... STATUS from infrastructure Epic (M effort) |
2 | Revalidation Connections - Overview | Epic summary - TIS21-3592Getting issue details... STATUS (2 done and 1 in BL -3734) - TIS21-3594Getting issue details... STATUS (1 done and 2 BL - 3772 and 3769) - TIS21-3595Getting issue details... STATUS (1 done and epic completed) - TIS21-3596Getting issue details... STATUS (Epic not finished with 5 in the BL - 3958; 3961; 3962; 3963; 3964; 3965 *** we must complete refinement of the stories in this Epic ***) - TIS21-3735Getting issue details... STATUS (2 done, 3 BL - 4041; 4038; 4039; 4040. 1 refinement 3774 (re-sync), 3874 in for dev (above). Can we devise a sequence of work / plan for how we are going to deliver the MVP and associated change inc. decommissioning V1 >>> the prerequisite is getting the epics completed. <<< |
3 | Revalidation reporting research / discovery | In progress → UR - - TIS21-4013Getting issue details... STATUS Next step Alpha? This is primarily data/ user research/? usability testing work so assume no impact on developers (is this a correct assumption)- |
4 | ESR | Ready → File management → - TIS21-146Getting issue details... STATUS |
5 | Programme Membership | Refinement Cross-Team for tickets in backlog TIS21-2399 &TIS21-2403. |
6 | Bulk Upload | |
7 | Data work | ESR reporting → |
8 | Technical improvement | |
9 | Retro actions | (new) Fiaz liaison → - TIS21-4103Getting issue details... STATUS
- TIS21-4217Getting issue details... STATUS |
10 | Roadmap review | Can we just sense check? TIS Admin product roadmap.pptx Explode-out revalidation to produce a Revalidation Roadmap |
Goal(s) for the next Iteration:
Statement:
Focussing on
Revalidation connections - to deliver value
To define the MVP delivery plan so it can be socialised
To continue UR work on reporting into Alpha
Team availability (e.g., Leave & Events):
User Research Sessions - a number of the team
Pepe A/L 7 Feb-20th Feb
Steve A/L 13 Feb -17th Feb
Non-Kanban work (this iteration):
Post funding. Planning to get a call in with James, Ade B, Ade A and Rob
Collate ESR work, specifically list of issues. Planning to get a call in. Rob/?Pepe
Review survey results. Meeting to be planned in to discuss findings with the involvement
Work lined up for the iteration | ||
---|---|---|
1 | Revalidation - Connections | - TIS21-3774Getting issue details... STATUS - next work in line (for refinement) - TIS21-3874Getting issue details... STATUS Look at - TIS21-4041Getting issue details... STATUS from infrastructure Epic (M effort) |
2 | Revalidation Connections - Overview | Epic summary - TIS21-3592Getting issue details... STATUS (2 done and 1 in BL -3734) - TIS21-3594Getting issue details... STATUS (1 done and 2 BL - 3772 and 3769) - TIS21-3595Getting issue details... STATUS (1 done and epic completed) - TIS21-3596Getting issue details... STATUS (Epic not finished with 5 in the BL - 3958; 3961; 3962; 3963; 3964; 3965 *** we must complete refinement of the stories in this Epic ***) - TIS21-3735Getting issue details... STATUS (2 done, 3 BL - 4041; 4038; 4039; 4040. 1 refinement 3774 (re-sync), 3874 in for dev (above). Can we devise a sequence of work / plan for how we are going to deliver the MVP and associated change inc. decommissioning V1 >>> the prerequisite is getting the epics completed. <<< |
3 | Revalidation reporting research / discovery | In progress → UR - - TIS21-4013Getting issue details... STATUS Next step Alpha? This is primarily data/ user research/? usability testing work so assume no impact on developers (is this a correct assumption)- |
4 | ESR | Ready → File management → - TIS21-146Getting issue details... STATUS |
5 | Programme Membership | Refinement Cross-Team for tickets in backlog TIS21-2399 &TIS21-2403. |
6 | Bulk Upload | |
7 | Data work | ESR reporting → - TIS21-3980Getting issue details... STATUS Stan to create Bug ticket as a follow on work in the iteration. |
8 | Technical improvement | Trainee team ticket we need sight of → - TIS21-532Getting issue details... STATUS |
9 | Retro actions | (new) Workshop for Jira → - TIS21-4102Getting issue details... STATUS (new) Fiaz liaison → - TIS21-4103Getting issue details... STATUS |
10 | Roadmap review | Can we just sense check? TIS Admin product roadmap.pptx Explode-out revalidation to produce a Revalidation Roadmap |
Goal(s) for the next Iteration:
Statement:
Focussing on
Revalidation connections - to deliver value
To define the MVP delivery plan so it can be socialised
To continue UR work on reporting into Alpha
Team availability (e.g., Leave & Events):
User Research Sessions - a number of the team
Anita on A/L 2nd Feb -10 Feb
13 Feb on A/L
Rob to confirm A/leave next week?
Pepe A/L 7 Feb-20th Feb
Everyone: Hack Retro TBC
Non-Kanban work (this iteration):
Post funding. Planning to get a call in. y
Collate ESR work, specifically list of issues. Planning to get a call in. y
Review survey results (pre-refinement/refinement this iteration). Perhaps Stan can help with result analysis? y
Work lined up for the iteration | ||
---|---|---|
1 | Revalidation - Connections | Complete → - TIS21-4116Getting issue details... STATUS Will this unblock the rest of Connections. If so, what next? Investigation - TIS21-3774Getting issue details... STATUS - next work in line (for refinement) - TIS21-3874Getting issue details... STATUS Look at - TIS21-4041Getting issue details... STATUS from infrastructure Epic (M effort) |
2 | Revalidation Connections - Overview | Epic summary - TIS21-3592Getting issue details... STATUS (2 done and 1 in BL -3734) - TIS21-3594Getting issue details... STATUS (1 done and 2 BL - 3772 and 3769) - TIS21-3595Getting issue details... STATUS (1 done and epic completed) - TIS21-3596Getting issue details... STATUS (Epic not finished with 5 in the BL - 3958; 3961; 3962; 3963; 3964; 3965 *** we must complete refinement of the stories in this Epic ***) - TIS21-3735Getting issue details... STATUS (2 done, 3 BL - 4041; 4038; 4039; 4040. 1 refinement 3774 (re-sync), 3874 in for dev (above). Can we devise a sequence of work / plan for how we are going to deliver the MVP and associated change inc. decommissioning V1 >>> the prerequisite is getting the epics completed. <<< |
3 | Revalidation reporting research / discovery | In progress → UR - - TIS21-4013Getting issue details... STATUS Next step Alpha? This is primarily data work so assume no impact on developers (is this a correct assumption)- |
4 | ESR | Ready → File management → - TIS21-146Getting issue details... STATUS |
5 | Programme Membership | Refinement Cross-Team for tickets in backlog TIS21-2399 &TIS21-2403. |
6 | Bulk Upload | |
7 | Data work | ESR reporting → - TIS21-3980Getting issue details... STATUS Stan to create Bug ticket as a follow on work in the iteration. |
8 | Technical improvement | Trainee team ticket we need sight of → - TIS21-532Getting issue details... STATUS |
9 | Retro actions | Review attendance → - TIS21-4004Getting issue details... STATUS (new) Workshop for Jira → - TIS21-4102Getting issue details... STATUS (new) Fiaz liaison → - TIS21-4103Getting issue details... STATUS |
10 | Roadmap review | Can we just sense check? TIS Admin product roadmap.pptx Explode-out revalidation to produce a Revalidation Roadmap |
Goal(s) for the next Iteration:
Statement:
Focussing on
Revalidation connections - to deliver value
To define the MVP plan so it can be socialised
To start the UR work on reporting
Team availability (e.g., Leave & Events):
User Research Sessions - a number of the team
Everyone: Hack Day
Non-Kanban work (this iteration):
Recruitment (Tracker) and update from Anita… https://hee-nhs-tis.slack.com/archives/C02EWCJR1MX/p1669895586096139
Post funding. ?
Collate ESR work, specifically list of issues. (Rob)
NI investigation. Ongoing. (Rob)
GMC show and tell - are there thoughts around this?
Want to resurrect user satisfaction survey, but unsure of timings.
Review survey to go out. Perhaps Stan can help with result analysis?
Work lined up for the iteration | ||
---|---|---|
1 | Revalidation - Connections | Ready → Maven workflow → - TIS21-3880Getting issue details... STATUS Agree to rapidly refine - TIS21-3774Getting issue details... STATUS and put at the top of Ready for Development so it is worked on first. Then once 3774 is advanced work through what else is brought onto the Kanban. Look at - TIS21-4041Getting issue details... STATUS from infrastructure Epic (M effort) |
2 | Revalidation Connections - Overview | Epic summary - TIS21-3592Getting issue details... STATUS (2 done and 1 in BL -3734) - TIS21-3594Getting issue details... STATUS (1 done and 2 BL - 3772 and 3769) - TIS21-3595Getting issue details... STATUS (1 done and epic completed) - TIS21-3596Getting issue details... STATUS (Epic not finished with 5 in the BL - 3958; 3961; 3962; 3963; 3964; 3965 *** we must complete refinement of the stories in this Epic ***) - TIS21-3735Getting issue details... STATUS (2 done, 3 BL - 4041; 4038; 4039; 4040. 1 refinement 3774 (re-sync), 3874 in for dev (above). Can we devise a sequence of work / plan for how we are going to deliver the MVP and associated change inc. decommissioning V1 |
3 | Revalidation-related | Ready → Testing → - TIS21-3880Getting issue details... STATUS |
4 | Revalidation reporting research / discovery | In porgress → UR - - TIS21-4013Getting issue details... STATUS |
5 | ESR | Ready → File management → - TIS21-146Getting issue details... STATUS |
6 | Programme Refactoring | - TIS21-2403Getting issue details... STATUS to be refined prob Yafang, James and Reuben |
7 | Data work | In progress ESR reporting → - TIS21-3946Getting issue details... STATUS ESR reporting → - TIS21-3980Getting issue details... STATUS Revalidation and Metabase → - TIS21-3979Getting issue details... STATUS |
8 | Technical improvement | We’ve got a couple of stories related to Live Defects. We’ll focus on those and the tech platform for Connections. |
9 | Retro actions | Onboarding → - TIS21-4003Getting issue details... STATUS Hack day → - TIS21-3986Getting issue details... STATUS Review attendance → - TIS21-4004Getting issue details... STATUS (new) Workshop for Jira → - TIS21-4102Getting issue details... STATUS (new) Fiaz liaison → - TIS21-4103Getting issue details... STATUS |
10 | Roadmap review | Can we just sense check? TIS Admin product roadmap.pptx Explode-out revalidation to produce a Revalidation Roadmap |
Add Comment