Versions Compared

Key

  • This line was added.
  • This line was removed.
  • Formatting was changed.

...

Jira Legacy
serverSystem JIRA
columnskey,summary,type,assignee,status,business value,story points (effort),priority (bv*sp)
maximumIssues100
jqlQueryproject = tisnew AND type not in (Sub-task, Epic) AND (assignee not in (benjamin.witton, Chris.Norman, Nazia.Akhtar, david.short, james.harris) OR assignee is EMPTY) AND sprint="Sprint 66" and status not in ("Not required") ORDER BY status DESC, assignee ASC, cf[11231] ASC, cf[11233] ASC, cf[11237] ASC
serverId4c843cd5-e5a9-329d-ae88-66091fcfe3c7

Item

TIS Ref / Owner

Status

Description of workLink. e.g. to working software https://apps.tis.nhs.uk/
(note: use Dev for obfuscated data)
Loom video of completed work https://www.useloom.com/

Technical debt & Non-functional requirements:











Knowledge transfer:

  1. Confluence housekeeping - especially deleting documentation that is out of date. Ongoing
  2. Dev standards (Dev meeting / series of meetings). Ongoing
  3. Pairing / Mobbing
  4. Git-commit messages
  5. Walk-throughs (prep as you go - links?). 
  6. Architectural level diagrams
  1. Andy Nash (Unlicensed)


  2. All Dev team
  3. All Dev team
  4. All Dev team
  5. All Dev team
  6. All Dev team

Ongoing














Resource Planning:

Andy Nash (Unlicensed)


Ongoing recruitment push:

  • two new Apprentice Devs (Manchester) confirmed to be starting next Sprint (4 Feb).

Outstanding vacancies

  • London: 1*DevOps engineer, 1*FSD and 1*FED
  • Manchester: 1*Lead Dev, 1*FED and 1*Junior Dev

...