Sprint 77 Review (2019-07-09)

Availability

(assume Team Availability Calendar is up to date, otherwise, everyone was available for 8.5 days of the 2-week Sprint)

Full team availability 8.5-day Sprint * 8 dev team members (adjusted as below)63.5 days

Yafang
Ola -1, Pepe -1
Andy -2, JohnO -2 
Jay -6
John -6.5, Simon -6.5, 


Total team availability this Sprint61%

POs present a review of Sprint goals and other committed work

Sprint Goal: Service Status: Connect Admins page message displayed on front end. AND... TIS: Widening what's visible and searchable in ESR and Programme roles.
Plus other committed-to work:
  • ESR - Handling multiple applicants per deanery number in the DNF/C Files (Fix the code) : PART I.

POs supported by Dev team provide narrative on why, and what, emergency work was brought into the Sprint and which committed-to tickets were moved out as a result

Live Issues:

type summary story points (effort) assignee created status
Loading...
Refresh

Dev team demo 'done' work contributing to those goals (no more reference to specific list of Jira tickets, and no more reference to work not 'done')

ItemDemo - from Prod URL where feasibleDemo link

1.

Service status
2.Extend logic for Programme role for Placement Planner users

Non-Programme Admin User Demo: https://stage-apps.tis.nhs.uk/admin

Programme Admin User Demo: https://stage-apps.tis.nhs.uk/admin

3.Replace backend query param sanitizerA new method developed by the team to sanitize search queries has now been implemented in all services barring Revalidation.
4.ESR - Handling multiple applicants per deanery number in the DNF/C Files (Fix the code): PART I
5.Supporting documents for Placement Planner tool live defect

i.


ii.


iii.

Stakeholders / Users invited to query / interrogate / applaud (after Sprint Review POs convert consensus inputs into backlog tickets, giving the option to consider them in the coming Sprint Planning)

Review Sprint Goal: Service Status: Connect Admins page message displayed on front end. AND... TIS: Widening what's visible and searchable in ESR and Programme roles.

POs present the roadmap

Non Tech Link: https://ext.prodpad.com/ext/roadmap/58c41bcc06a77c08acc891aed47aca7210fdfe03

Next Sprint priorities