Sprint 60 Review (2018-10-31)
Availability
(assume Team Availability Calendar is up to date, otherwise, everyone was available for 9 days)
Alistair Joanne Matt Ola Roope Simon | -5 -2 -4 -2 -2 -4 |
---|
Sprint Priorities
The following list was the prioritisation output from Sprint Planning - largely a stabilisation Sprint:
- K&S on Azure
- User Management
- Reval snaglist
- Load/Stress tests
- Enabling soft delete
- Bulk upload changes: TIS Placement IDs and parallel processing
- Investigate adding Audit function
Contents
The following items to be shared by team members during this sprint review
Item | TIS Ref / Owner | Status | Description of work | Link. e.g. to working software https://apps.tis.nhs.uk/ (note: use Dev for obfuscated data) Loom video of completed work https://www.useloom.com/ | |
---|---|---|---|---|---|
Production Application releases / updates | Anyone in the team now we have the new pipeline! | Assign fix number in Jira for anything committed - so POs have a record of each Sprint's releases (even though they are done incrementally throughout the Sprint) | Bugs Stories | ||
NHS HEE TIS UX/UI: Colour palette and accessibility | Matt Leech (Unlicensed) | ||||
Technical debt & Non-functional requirements: | |||||
Admins UI security vulnerabilities in dependencies | |||||
E2E testing | |||||
Knowledge transfer: | |||||
|
| Ongoing | Making some progress - but long way still to go... | ||
Resource Planning: | Manchester: BA, UI/UX been offered. Scrum Master being offered. No Devs as yet. |
Slack: https://hee-nhs-tis.slack.com/
Jira issues: https://hee-tis.atlassian.net/issues/?filter=14213